Construction Update - August 18
Phase 2 (Nathan Lane, 56th Avenue, and Hwy 169 Service Drive north of 54th Avenue)
Utility work has started in Phase 2 with water valve repairs and hydrant replacements. The contractor also removed the street pavement at the intersection of 56th Avenue and Nathan Lane. Next week the utility work continues with storm sewer installation at the intersection of 56th Avenue and Nathan Lane. Concrete curb work will also begin early next week throughout Phase 2. The intersection at 56th Avenue and Nathan Lane is currently closed and will be until construction is complete at the realigned intersection.
Access to businesses and residences in the Nathan Area north of 56th Avenue will remain open to traffic from Bass Lake Road. For businesses and residences south of 56th Avenue, access will remain open to traffic from Schmidt Lake Road. No vehicles will be able to pass through the intersection of 56th Avenue and Nathan Lane until further notice. Delays should be anticipated during construction with narrowed roadways and detours in and around the project area.
A project help line has been established for resident questions or concerns during construction; the help line number is (763) 331-8619. Alternatively, residents can contact the construction observer Arianna Christian at 612-398-8949, or project manager Nick Amatuccio at 612-965-3926 or email nickam@bolton-menk.com.
|
|
|
|