Construction Update - August 11
Phase 1 (54th Avenue and Hwy 169 Service Drive south of 54th Avenue) The contractor is finishing up final turf restoration items in Phase 1 this week.
Phase 2 (Nathan Lane, 56th Avenue, and Hwy 169 Service Drive north of 54th Avenue)
The contractor started work this week with pavement removals and utility work. 56th Avenue is currently closed at Nathan Lane.
Beginning today, Nathan Lane will be closed between 56th Avenue and 57th Avenue for pavement removals and storm sewer installation. Concrete curb work will also begin later next week throughout Phase 2.
Access to businesses and residences in the Nathan Area north of 56th Avenue will remain open to traffic from Bass Lake Road. For businesses and residences south of 56th Avenue, access will remain open to traffic from Schmidt Lake Road. However, delays should be anticipated during construction with narrowed roadways and detours in and around the project area.
A project help line has been established for resident questions or concerns during construction; the help line number is (763) 331-8619. Alternatively, residents can contact the construction observer Arianna Christian at 612-398-8949, or project manager Nick Amatuccio at 612-965-3926 or email nickam@bolton-menk.com.
|