Construction Update - August 4
The contractor has completed installation of new sanitary sewer by Plymouth Dog Park, and is currently installing water main in this area of the project. After completion of the water main, installation of storm sewer will begin on Chankahda Trail between Inland Lane and Archer Lane.
Next week the contractor is planning to finish grading of the trails between Archer Lane and Vicksburg Lane in preparation for paving the following week. Also scheduled for next week in this area of the project is the installation of the remaining concrete curb and gutter and topsoil.
|
|
|
|