Construction Update July 28
The Gleason Lake Drive and Vicksburg Lane intersection remains closed to traffic. The posted detour includes County Road 6, Interstate 494, and Highway 12. During construction, access will be maintained for the local adjacent neighborhoods on Townes Road and Black Oaks Lane via Gleason Lake Road to the south, but access may change as construction progresses.
Additional intersections along the project corridor will be periodically closed to allow for construction activities. The contractor will maintain access to property owners who live in the project area, however, delays can be expected during construction activity.
Phase 2 - Gleason Lake Drive between Vicksburg Lane and Ranchview Lane The contractor plans continue gravel work and begin pouring the curb and gutter at the Vicksburg intersection the week of July 31st.
Phase 1B - Gleason Lake Drive between Ranchview Lane and Niagara Lane Work in this phase is almost complete. Sod will be installed in this section later in the summer when it is less hot, providing better conditions for vegetation establishment.
Phase 1B - Niagara Lane Paving of the road and trail is planned for the week of July 31st.
Phase 3 - Gleason Lake Drive between Niagara Lane and Carlson Parkway The contractor is continuing to connect property owners to a temporary water service. Owners will be on temporary water until the utilities in the street are replaced. Utility replacement is planned for mid-late August.
|