Construction Update - June 30
The contractor continued construction in Phase 1 (54th Avenue and Hwy 169 Service Drive from 54th Avenue to Schmidt Lake Road) this week with utility work and concrete curb replacement. Storm sewer installation occurred on the Schmidt Lake Road and 51st Avenue intersections with the Hwy 169 Service Drive, and concrete was poured at Schmidt Lake Road, the Nathan Lane cul-de-sac, and along most of the Hwy 169 Service Drive.
All lanes on Schmidt Lake Road are anticipated to be opened back up to traffic at the end of the day Friday, June 30th. The Hwy 169 Service Drive will remain closed at the Schmidt Lake Road intersection through the month of July.
The intersection of 54th Avenue and Hwy 169 Service Drive will be closed on Wednesday, July 5th, to work on storm sewer, curb and gutter placement, and road grading. It is anticipated this intersection will remain closed for approximately two weeks. Work on other miscellaneous utility, curb, and grading will continue throughout all of Phase 1 next week.
Access to businesses and residences in the Nathan Area will remain open to traffic by using Bass Lake Road and Nathan Lane for properties on and to the north of 54th Avenue. Properties south of 54th Avenue can access by using Schmidt Lake Road/Nathan Lane/51st Avenue. Delays should be anticipated during construction with narrowed roadways and detours in and around the project area.
|