Construction Update - June 2
The contractor for Phase 2 of the Chankahda Trail Reconstruction Project has completed installation of storm sewer in the Vicksburg Lane intersection. Installation of sanitary sewer between Archer Lane and Vicksburg Lane has also been completed. Next week the contractor will continue with installation of storm sewer between Archer Lane and Vicksburg Lane. Installation of concrete curb and gutter is also scheduled to be installed at the Vicksburg Lane intersection next week.
|
|
|
|