Phase 1 Construction Update - April 21, 2023
The contractor anticipates resuming construction on Phase 1 of Chankahda Trail on Monday, April 24th. Remaining work includes minor punch list items as well as remaining work at the County Road 101 and Chankahda Trail intersection. The remaining work is anticipated to be completed around the end of May.
The roadway will remain open to traffic during this time but will include intermittent lane closures. Please exercise caution when driving through the work area and follow all construction signage.
|
|
|
|