Phase 1 Construction Update – November 23
The contractor has completed installation of retaining walls, installation and paving of the section of roadway from Meadow Ridge Elementary to Peony Lane, as well as paving trails. The contractor anticipates to fully open Chankahda Trail to traffic later this afternoon. The contractor will continue to work on minor miscellaneous items for the next week, which will complete work for 2022.
The project will resume in early 2023, for completion of outstanding items at the Chankahda Trail and County Road 101 intersection. This work is anticipated to take a few weeks to finish under traffic.
|
|
|
|