Phase 1 Construction Update – Aug. 12, 2022
The contractor is currently installing storm sewer in the intersection of County Road 47 and Maple Grove Parkway/Peony Lane. Grading of the intersection is scheduled for next week with installation of concrete curb and gutter to follow. As a reminder, the County Road 47/Peony Lane/Maple Grove Parkway intersection is fully closed to traffic. The detour for Peony Lane/Maple Grove Parkway consists of Highway 55, County Road 101 and Bass Lake Road. The detour route for County Road 47 consists of Vicksburg Lane, Bass Lake Road and County Road 101.
A detour map is available on the project webpage.
|
|
|
|