Phase 1 Construction Update
The contractor is currently installing storm sewer and grading the portion of County Road 47 between Peony Lane and Elm Creek. The contractor anticipates to fully close the intersection of County Road 47 and Peony Lane/Maple Grove Parkway on August 8th for an estimated period of 3 weeks. Signs providing advanced notice of the closure are currently posted and a detour route will be posted once the closure is in effect. The detour for Peony Lane/Maple Grove Parkway consists of Highway 55, County Road 101, and Bass Lake Road. The detour route for County Road 47 consists of Vicksburg Lane, Bass Lake Road, and County Road 101. A detour map is available on the project webpage.
|
|
|
|