 Construction Update - June 22
The contractor has paved the initial layers of pavement on the portion of Vicksburg Lane from Highway 55 to 35th Avenue. This week they plan to install remaining concrete and start restoration activities. The contractor plans to install the final layer of asphalt on the roadway and temporary pavement markings on Monday of next week.
On Tuesday, June 28th, the contractor anticipates closing Vicksburg Lane from 35th Avenue to Old Rockford Road to traffic to facilitate construction on stages 2 and 3 of the project. A detour route will be posted once the closure occurs. Detour and staging layout information can be found on the project webpage.
The contractor will open the section of Vicksburg Lane from Highway 55 to 35th Avenue to traffic on Tuesday, June 28th.
|
|
|
|