Footings and foundations for both north and south buildings are complete
Southbound parkway traffic scheduled to reopen when boat launch reopens
Construction on a new concessions pavilion area at Bde Maka Ska continues to progress, with building footings and foundations complete and utility work scheduled to begin in September.
The Bde Maka Ska boat launch, closed since June 6, will reopen beginning Saturday, September 24 through Monday, October 10. Hours will be 6 am-9 pm.
Southbound East Bde Maka Ska Parkway, closed to vehicle traffic from Lake Street to 36th Street since Aug. 1, will reopen during this time as well.
An illustration of the new Bde Maka Ska pavilion site
About the Bde Maka Ska Pavilion Rebuild Project
The project will create two new buildings, including new, all-gender accessible restrooms and ample outdoor public seating to replace the building that burned down in 2019.
The Minneapolis Sailing Center and Wheel Fun Rentals are operating at northeast Bde Maka Ska this season.
Work will continue throughout the year and the new buildings are scheduled to open next summer. Please stay away from construction areas and follow all detour signs.
Visit the Bde Maka Ska Refectory Rebuild project page and subscribe to email updates for periodic construction updates and information on trail or road closures related to this project.
To
learn more about this project and others, visit www.minneapolisparks.org/planning.
|