 A rendering of the new St. Anthony Parkway Bridge
New truss currently being assembled west of rail yard; parkway scheduled to reopen by fall 2017
All five spans of the old St. Anthony Parkway truss bridge
have been removed and work crews are currently assembling a large steel truss
that covers approximately three-fifths of the distance over Northtown Railyard. The truss will be installed later this spring.
New bridge pieces are delivered and assembled on St. Anthony Parkway, west of
the bridge. St. Anthony Parkway is scheduled to reopen by fall 2017.
The new bridge will include wider pedestrian and bike lanes that connect to nearby trails and existing sidewalks. Visit
www.stapbridge.com to view a timelapse of one of the old span removals,
a live webcam showing current
progress and other project details.
 An artist's sketch of the Northtown Yard Interpretive Area
Interpretive Area
The City of Minneapolis project also features an interpretive area next to the bridge with views of the skyline over Northtown Yard. Construction on the interpretive area is expected to be substantially complete by the end of 2017.
|