Green Line to open June 14
Elected, appointed and community leaders surround Metropolitan Council Chair Sue Haigh as she announced Jan. 22 at Union Depot Station that METRO Green Line (Central Corridor LRT) will begin service June 14.
To-do list for METRO Green Line’s grand opening
Yours:
Ours:
-
Take delivery of 20 additional light rail vehicles (LRVs) January-May
- Complete systems testing, inspections February-May
- Train 61 LRV operators late February to mid-April
- Fix cracked concrete intersections, adjust manhole elevations by mid-May
- Conduct pre-revenue service testing mid-April to mid-June
Read the opening day news release at http://bit.ly/1dYjD2Z
STAY OFF TRACKS — Scenes like the one above will become common in late February when daily tests of the Green Line’s systems begin.
Regular daily light rail vehicle tests will begin late February
Staying off Green Line tracks becomes critical in late February when daily tests will begin of the new light rail vehicles.
Trains will run as often as 10 minutes apart, the same frequency as regular daily service.
“This means anytime is train time from now on. Expect to see a train at any time on any track from either direction,” said Mike Conlon, director of rail and bus safety for Metro Transit. “Safety is our shared responsibility.”
Remember these four basic safety rules:
- Always stay off the tracks
- Stay off station platforms until service begins in 2014. After service begins, a ticket will be required to enter platforms
- Look both ways for oncoming trains
- Cross only at intersections and legal mid-block crosswalks
|