Construction crews have installed the steel framework and roof panels for the new METRO Gold Line station on Concordia Avenue. Since August, crews have been working diligently to build the foundation for the stations on St. Anthony and Concordia Avenues, conducting underground electrical work and building bus stop pads.
Crews will finish major construction at both stations by the end of 2026. The new stations will include heating and lighting, real-time signs, ticket machines, security cameras and emergency call boxes.
These stations will unlock a new connection when the bus rapid transit line extends further west on March 27, 2027. The extended Gold Line will replace express Route 94, which runs between St. Paul and Minneapolis, and will eliminate the need to transfer in St. Paul, making the commute more seamless. The Gold Line will serve most existing stops in downtown St. Paul and will stop at existing Bus Rapid Transit (BRT) stations on 7th and 8th streets in Minneapolis. Riders will be able to connect to the Green Line extension’s Royalston Ave/Farmers Market Station from 7th St. & 5th Ave. Station in downtown Minneapolis.
Temporary METRO Gold Line stations in downtown Minneapolis and St. Paul
As part of the METRO Gold Line extension, Metro Transit will install temporary stations in downtown Minneapolis and St. Paul to support service until permanent station improvements are completed.
In downtown Minneapolis, temporary eastbound and westbound stations will be located near the intersection of 7th St. S and 11th Ave. S, just before the intersection. These temporary facilities will serve riders until permanent stations are constructed in coordination with the City of Minneapolis' planned 7th St. Reconstruction Project, currently anticipated in 2029. Once completed, the permanent stations will be located just beyond the intersection.
In downtown St. Paul, there will be a third temporary station on 5th St. and 7th St. W near Grand Casino Arena. This stop currently serves Route 94, among other express and local routes.
To provide a consistent rider experience, Metro Transit will add off-board payment equipment and real-time signage to all of the temporary stations by the end of 2026.
 |
The extended METRO Gold Line is set to open on Saturday, March 27, 2027, and Metro Transit is planning a community celebration to mark the occasion. Remember to save the date! We will share information as more details become available.
-
Watch this video and learn more about BRT.
-
Connect with Gold Line Staff to learn about construction updates
-
If you are interested in learning more about the Gold Line project, please reach out to Sia Bell, Community Outreach Coordinator, at 763-358-0219 or email goldline@metrotransit.org
Follow us on social media
|