Gold Header Construction Update

METRO Gold Line BRT Construction Update

Web: metrotransit.org/gold-line-construction

Construction Hotline: 651-602-1919

Email: goldline@metrotransit.org

Twitter: @GoldLineBRT

View an interactive map for specific construction location information.

View a timelapse video of bridge construction in St. Paul, Maplewood, Oakdale, and Woodbury.

Note: This is the last weekly construction update. We will send out monthly updates as we approach opening day March 22, 2025. Thank you for subscribing to the Gold Line construction updates.

 

Construction this winter

Fencing and signage are being installed throughout the project corridor over the winter. Construction crews will continue working over the winter on station platforms and remaining construction items. Metro Transit will turn on and test station amenities over the winter. Remaining landscaping work will occur in spring 2025.  

No parking reminder

Pay attention to new parking and access restriction signage that has and will continue to be installed over the next few weeks. Areas that are signed as no parking are subject to local citation and towing regulations.

Downtown St. Paul highlights

  • In Downtown St. Paul, crews continue station construction.

East St. Paul highlights

  • Crews work on the Mounds Boulevard and 3rd Street signal intersection.  
  • Crews continue to drill fence posts and install fencing.
Crews install fence posts along Old Hudson Road near Sun Ray Shopping Center

Image: Crews install fence posts along Old Hudson Road near Sun Ray Shopping Center

Maplewood/Landfall/Oakdale highlights

  • Crews continue to drill fence posts and install fencing.
Crews install glass at the Helmo Station

Image: Crews install glass at the Helmo Station

Woodbury highlights

  • Crews continue to drill fence posts and install fencing.
  • Construction continues for the new Woodlane Park & Ride near the intersection of Woodlane Drive and Guider Drive.

Gold Line Extension to Minneapolis in 2027

In 2027, Gold Line service will extend to downtown Minneapolis, allowing people to travel more efficiently across the metro. The Gold Line Extension will bring new, enhanced stations to Interstate 94 and Snelling Avenue as well as near U.S. Bank Stadium. In Minneapolis, the Gold Line will utilize existing bus rapid transit stations on 7th and 8th streets and bring riders to the METRO Green Line Extension’s Royalston Avenue/Farmers Market Station.

When in service, the Gold Line Extension will replace Route 94, the express route operating between downtown Minneapolis and downtown St. Paul, which currently serves around 800 riders each weekday. The Gold Line will provide a one-seat ride and offer frequent service seven days a week. For more information, visit: https://www.metrotransit.org/gold-line-extension.