METRO Gold Line BRT Construction Update

Having trouble viewing this email? View it as a Web page

November 22, 2024

Gold Header Construction Update

METRO Gold Line BRT Construction Update

Web: metrotransit.org/gold-line-construction

Construction Hotline: 651-602-1919

Email: goldline@metrotransit.org

Twitter: @GoldLineBRT

View an interactive map for specific construction location information.

View a timelapse video of bridge construction in St. Paul, Maplewood, Oakdale, and Woodbury.

I-694 Overnight Closures

Overnight closures of I-694 in Oakdale were rescheduled due to weather. Southbound I-694 will close overnight between Highway 36 and I-94 on Friday, November 22, Sunday, November 24, and Monday, November 25. I-94 ramps to I-694 will close at 9pm. I-694 will reopen by 5am each morning and ramps by 6am. Follow the posted detour route.

694 new map

Image: I-694 Overnight Closure Map

What to expect this winter

Construction activities are winding down across the project corridor but will continue over the winter. Crews will wrap up asphalt paving, traffic signals, signing, lighting, and landscaping in the coming weeks. Minor finish work will continue throughout the corridor through January, including installations at station platforms and site restoration. Metro Transit will be testing operations on the route, expect to see buses running on the guideway. Any remaining landscaping work will occur in spring 2025. Gold Line will open for service on March 22, 2025.

Construction activities this week

Construction is ongoing in St. Paul, Maplewood, Oakdale, and Woodbury. Expect to see construction crews paving asphalt along the project corridor over the next few weeks. Fencing is being installed throughout the project corridor over the next few weeks. Trails along the project corridor are being completed.

Pedestrian and bike trails

The Gold Line project includes new trail and new connections between existing trail, creating continuous shared use trail between Woodlane Station in Woodbury and Sun Ray Station in St. Paul. Crews are completing final trail work and expect all trails to be paved and ready for use by the end of next week.

Trail paving near White Bear Avenue.

Image: Trail paving near White Bear Avenue.

No parking reminder

Pay attention to new parking and access restriction signage that has and will continue to be installed over the next few weeks. Areas that are signed as no parking are subject to local citation and towing regulations.

Downtown St. Paul highlights

Ongoing:

  • Crews continue station construction along with road and sidewalk restoration.

Traffic:

  • Intermittent lane closures may occur at station areas as needed.

East St. Paul highlights

Upcoming:

  • The Ruth Street on-ramp to I-94 westbound will close during the daytime on Tuesday, November 26, and Wednesday, November 27.

Ongoing:

  • Crews install signage along the bus guideway between Johnson Parkway and Etna Street.
  • Crews install fencing around the White Bear Avenue area.
  • The intersection of Old Hudson Road and Hazel Street is reopened. Crews paved the intersection and filled areas with topsoil.
  • At the Sun Ray Park & Ride, crews install cameras and pour concrete for the driveway.
  • Crews install fencing along Old Hudson Road between Ruth Street and McKnight Road.

Traffic Impacts:

  • The intersection of Old Hudson Road and Hazel Street reopens Friday, November 22.
Crews install railings at the Earl Station

Image: Crews install railings at the Earl Station

Maplewood/Landfall/Oakdale highlights

Upcoming:

  • Overnight closures of I-694 in Oakdale were rescheduled due to weather. Southbound I-694 will close overnight between Highway 36 and I-94 on Friday, November 22, Sunday, November 24, and Monday, November 25. I-94 ramps to I-694 will close at 9pm. I-694 will reopen by 5am each morning and ramps by 6am. Follow the posted detour route.

Ongoing:

  • Crews install signage and trails along Old Hudson Road between McKnight Road and Century Avenue/Highway 120.
  • This week crews installed piles along Hudson Boulevard between Dellwood Lane and west of Greenway Avenue. Crew will install curbs east of Dellwood Lane this week and expect to pave the roadway next week.
  • Along Hudson Boulevard between Greenway Avenue and Greystone Avenue crews install fencing, turn the new signal on, pave trails, and install guard rail along I-94.
  • Greenway Station platform construction continues. Crews install glass and electrify the platform.
  • Crews install signage along Hadley Avenue between Hudson Boulevard and 4th Street.
  • Crews remove temporary utility supports underneath the reconstruction 4th Street bridge.
  • Construction at Helmo Park & Ride station area continues as crews lay gravel.

Traffic impacts:

  • Hudson Boulevard is closed between Dellwood Lane and west of Greenway Avenue. Businesses access will be maintained from Greenway Avenue.
Hudson Boulevard Business Access Map

Image: Hudson Boulevard Business Access Map

Crews plant trees at the Maplewood Station

Image: Crews plant trees at the Maplewood Station

Crews pour concrete at the Greenway Station

Image: Crews pour concrete at the Greenway Station

Woodbury highlights

Upcoming:

  • The northern driveway exit at Tamarack Hills on the east side of Bielenberg Drive is closed through November 27 as crews work in the area. Cars will be able to enter the driveway during this closure.

 Ongoing:

  • Crews install fencing along Bielenberg Drive near Nature Path. Anticipate daytime trail closures.
  • Construction continues for the new Woodlane Park & Ride near the intersection of Woodlane Drive and Guider Drive.
  • See Washington County Service Center Project listed under the “Nearby Projects Under Construction” section for additional traffic impacts to this area.

Traffic impacts:

  • Lane closures in the work zones on Guider Drive, Bielenberg Drive, and Tamarack Road continue.  
Woodbury Construction Map

Image: Woodbury Construction Map

Gold Line Extension to Minneapolis in 2027

In 2027, Gold Line service will extend to downtown Minneapolis, allowing people to travel more efficiently across the metro. The Gold Line Extension will bring new, enhanced stations to Interstate 94 and Snelling Avenue as well as near U.S. Bank Stadium. In Minneapolis, the Gold Line will utilize existing bus rapid transit stations on 7th and 8th streets and bring riders to the METRO Green Line Extension’s Royalston Avenue/Farmers Market Station.

When in service, the Gold Line Extension will replace Route 94, the express route operating between downtown Minneapolis and downtown St. Paul, which currently serves around 800 riders each weekday. The Gold Line will provide a one-seat ride and offer frequent service seven days a week. For more information, visit: https://www.metrotransit.org/gold-line-extension.