Web: metrotransit.org/gold-line-construction
Construction Hotline: 651-602-1919
Email: goldline@metrotransit.org
Twitter: @GoldLineBRT
View an interactive map for specific construction location information.
View a timelapse video of bridge construction in St. Paul, Maplewood, Oakdale, and Woodbury.
Starting on Sunday, November 17, anticipate overnight closures of I-694. Northbound I-694 will close starting at 10pm on November 17, 18, and 19 between 10th Street and I-94, followed by the closure of southbound I-694 at 10pm on November 20, 21, and 22 between Highway 36 and I-94. I-94 ramps to I-694 will close at 9pm. I-694 will reopen by 5am each morning. Follow the posted detour route.
Image: I-694 Overnight Closure Map
Construction activities are winding down across the project corridor but will continue over the winter. Crews will wrap up asphalt paving, traffic signals, signing, lighting, and landscaping in the coming weeks. Minor finish work will continue throughout the corridor through January, including installations at station platforms and site restoration. Metro Transit will be testing operations on the route, expect to see buses running on the guideway. Any remaining landscaping work will occur in spring 2025. Gold Line will open for service on March 22, 2025.
Construction is ongoing in St. Paul, Maplewood, Oakdale, and Woodbury. Expect to see construction crews paving asphalt along the project corridor over the next few weeks. Fencing is being installed throughout the project corridor over the next few weeks.
Downtown St. Paul highlights
Ongoing:
- Crews continue station construction along with road and sidewalk restoration.
Traffic:
- Intermittent lane closures may occur at station areas as needed.
East St. Paul highlights
Ongoing:
- Crews apply pavement markings at the Maple Street pedestrian bridge.
- Crews install fencing around the White Bear Avenue area.
- At Old Hudson Road and Van Dyke Street, crews install sidewalks and fill in areas with topsoil.
- The intersection of Old Hudson Road and Hazel Street is closed. Local access only. Crews grade the roadway, install curbs, driveway aprons, and sidewalks.
- At the Sun Ray Park & Ride, crews install cameras and pavement markings.
- Crews install fencing and pavement markings along Old Hudson Road between Ruth Street and McKnight Road.
- Near the McKnight Bridge area, crews finish installation of a stormwater pond.
Traffic Impacts:
- Maple Street pedestrian bridge is reopened.
- Hudson Road west of Maple Street is reopened.
- The intersection of Old Hudson Road and Hazel Street is closed through next week.
Maplewood/Landfall/Oakdale highlights
Upcoming:
- Starting on Sunday, November 17, anticipate overnight closures of I-694. Northbound I-694 will close starting at 10pm on November 17, 18, and 19 between 10th Street and I-94, followed by the closure of southbound I-694 at 10pm on November 20, 21, and 22 between Highway 36 and I-94. I-94 ramps to I-694 will close at 9pm. I-694 will reopen by 5am each morning. Follow the posted detour route.
Ongoing:
- Along the bus guideway between McKnight Road and Century Avenue/Highway 120, crews install planter beds, and guardrails.
- Crews install piles along Hudson Boulevard between Dellwood Lane and west of Greenway Avenue.
- Along Hudson Boulevard between Greenway Avenue and Greystone Avenue crews install a signal, curbs, driveway aprons, fencing, grade trails, and pave the roadway.
- Greenway Station platform construction continues.
- Crews stripe the roadway along Hadley Avenue between Hudson Boulevard and 4th Street.
- Construction at Helmo Park & Ride station area continues as crews lay gravel and install pavement markings.
Traffic impacts:
- Hudson Boulevard is closed between Dellwood Lane and west of Greenway Avenue. Businesses access will be maintained from Greenway Avenue.
Image: Hudson Boulevard Business Access Map
Image: Signage is installed at the Maplewood Station platform.
Woodbury highlights
Ongoing:
- Crews install fencing along Bielenberg Drive near Nature Path. Anticipate daytime trail closures.
- Construction continues for the new Woodlane Park & Ride near the intersection of Woodlane Drive and Guider Drive.
- See Washington County Service Center Project listed under the “Nearby Projects Under Construction” section for additional traffic impacts to this area.
Traffic impacts:
- Lane closures in the work zones on Guider Drive, Bielenberg Drive, and Tamarack Road continue.
Image: Woodbury Construction Map
Image:Crews install railings along Century Avenue/Highway 120.
Image: Crews construct medians along Hudson Boulevard near Greenway Station
In 2027, Gold Line service will extend to downtown Minneapolis, allowing people to travel more efficiently across the metro. The Gold Line Extension will bring new, enhanced stations to Interstate 94 and Snelling Avenue as well as near U.S. Bank Stadium. In Minneapolis, the Gold Line will utilize existing bus rapid transit stations on 7th and 8th streets and bring riders to the METRO Green Line Extension’s Royalston Avenue/Farmers Market Station.
When in service, the Gold Line Extension will replace Route 94, the express route operating between downtown Minneapolis and downtown St. Paul, which currently serves around 800 riders each weekday. The Gold Line will provide a one-seat ride and offer frequent service seven days a week. For more information, visit: https://www.metrotransit.org/gold-line-extension.