Construction activities this week

Construction activities continue throughout the project area. Expect to see construction crews in St. Paul, Maplewood, Oakdale, and Woodbury. View a timelapse video of bridge construction in St. Paul, Maplewood, Oakdale, and Woodbury. Expect to see construction crews paving asphalt along the project corridor over the next few weeks.

Upcoming closures

  • Starting in the evening on Friday, September 27, the Hwy 61 and Burns Avenue intersection will be put into a 4-way stop intermittently while signal work occurs. These conditions are expected to last through Saturday morning. Anticipate additional delays when travelling through this area. Plan an alternative route if possible.
  • Starting October 7, the Highway 61/Etna Street/Wilson Avenue intersection as crews reconstruct the intersection. During the closure, westbound I-94 to southbound Hwy 61 and northbound Hwy 61 to west I-94 will remain open. Eastbound I-94 from Etna Street or northbound Hwy 61 and Etna Street from Hwy 61 will be closed.

Downtown St. Paul highlights

Ongoing:

  • Crews continue station construction along with road and sidewalk restoration.

Traffic:

  • Intermittent lane closures may occur at station areas as needed.

East St. Paul highlights

Upcoming:

  • Starting October 7, the Highway 61/Etna Street/Wilson Avenue intersection as crews reconstruct the intersection. During the closure, westbound I-94 to southbound Hwy 61 and northbound Hwy 61 to west I-94 will remain open. Eastbound I-94 from Etna Street or northbound Hwy 61 and Etna Street from Hwy 61 will be closed.
  • Eastbound Wilson Avenue is anticipated to reopen at the end of next week.
  • Next week, Pacific Street between Mound Street and Forest Street in anticipated to reopen to traffic.

Ongoing:

  • Crews continue construction of the Maple Street pedestrian bridge. Crews pour concrete for curbs and continue bridge helix construction.
  • Crews pave asphalt along Pacific Street between Mound Street and Forest Street at the south end of the Maple Street pedestrian bridge.
  • Construction activities continue at the stormwater pond near the intersection of Griffith Street and Johnson Parkway as crews install drainage pipes.
  • Crews reconstruct curb and driveways along Wilson Avenue between Johnson Parkway and Etna Street.
  • Crews construct pedestrian ramps, sidewalks, signals, and a new trail along Hwy 61 north to the Etna Street and Wilson Avenue intersection.
  • At the White Bear Avenue bridge area, crews grade the area and install stormwater sewers along the bridge guideway.
  • Construction activities continue on the Sun Ray Park & Ride near Wilson Avenue and Pedersen Street as crews install underground stormwater sewer and a filtration basin. Next week crews will install curbs at the park and ride area.
  • Crews continue construction of the BRT bridge over McKnight Road and the McKnight Road pedestrian bridge.

Traffic Impacts:

  • Eastbound Wilson Avenue is closed between Johnson Parkway and Etna Street in east St. Paul. Access to properties will be maintained. No parking on Wilson Avenue during this work. Eastbound Wilson Avenue is anticipated to reopen end of next week.
  • Maple Street pedestrian bridge remains closed.
  • Hudson Road is closed to traffic just west of Maple Street. Local access to residences will be maintained.
  • Pacific Street is closed between Mound Street and Forest Street as crews continue constructing the Maple Street pedestrian bridge. Pacific Street is anticipated to reopen next week.
  • Concrete lanes adjacent to Hudson Road are future bus-only lanes for the Gold Line route. They are closed to regular vehicle traffic.
  • Lane closures on Hwy 61 and Burns Avenue near the intersection. Expect delays traveling through the area. Plan an alternative route if possible.
  • White Bear Avenue is closed until fall 2024 between Old Hudson Road and the eastbound I-94 on- and off-ramps.
  • The Sun Ray Park & Ride is being constructed on the southeast corner of Wilson Avenue and Pedersen Street. No parking will be allowed on Pedersen Street or part of Wilson Avenue during this work. Access to businesses and Sun Ray Shopping Center will be maintained.
  • Old Hudson Road is closed from the eastern driveway of Sun Ray shopping center entrance to McKnight Road. Access to Sun Ray shopping center is maintained via Ruth Street and Pedersen Street.
Maple Ped

Image: Mounds St. Closure Map

Sunray Business Access

Image: Sunray Business Access

Wilson Closure Map

Image: Wilson Avenue Access Map

Highway 61 & Burns Avenue Construction

Image: Highway 61 & Burns Avenue Construction

White Bear Closure Map

Image: White Bear Closure Map

Crews construct the bus guideway near the Sunray shopping center

Image: Crews construct the bus guideway near the Sunray shopping center

Crews construct the Sunray Park & Ride

Image: Crews construct the Sunray Park & Ride

Maplewood/Landfall/Oakdale highlights

Upcoming:

  • Next week, crews will pave asphalt on Hudson Road between McKnight Road and Century Avenue/Hwy 120.

Ongoing:

  • Along Hudson Road between McKnight Road and Century Avenue/Highway 120, crews grade trails, install topsoil, and backfill areas.
  • Crews install planter beds at the Maplewood Station.
  • Construction activities continue on Century Avenue/Highway 120. Crews install posts and curbs on the Century Avenue bridge.
  • See MnDOT I-94 Pavement Project, listed under “Nearby Projects Under Construction” section for additional traffic impacts to this area.
  • Crews install stormwater sewers and remove pavement along Hudson Road between Greenway Avenue and Graystone Avenue. At the Greenway Station, crews grade the area and construct station platforms.
  • Crews install curbs and signals along 4th Street between Hadley Avenue and I-694.
  • Crews resume work at the Helmo Park & Ride station area.
  • Crews install signals along 4th Street at the Hayward Avenue and Helmo Avenue intersections and install a boulder wall.

Traffic impacts:

  • 19th Street is closed near Hudson Road east of 3M.
  • Century Avenue reduced to one lane each direction near I-94.
  • Hudson Boulevard is restricted to one lane with a directional traffic signal between Century Avenue and Birch Lane.
  • Hudson Boulevard is closed east of Dellwood Lane and from Greystone Avenue to Hadley Avenue. Access to the city of Landfall and businesses west of Greenway Avenue from Century Avenue and Hudson Boulevard. Access to businesses east of Greenway Avenue is maintained from 10th Street and Greenway Avenue. Route 219 will continue to serve the Landfall community near Dellwood Lane and Hudson Boulevard.
  • Access to Apostolic Bible Institute at Hudson Boulevard and Hadley Avenue intersection is from Greenway Avenue and Hudson Boulevard.
  • 4th Street is closed between Hadley Avenue and Hayward Avenue, and from Hayward to just west of Helmo Avenue. The intersection of 4th Street and Hadley Avenue is closed.
  • The segments of 4th Street will be closed for the 2024 construction season as crews reconstruct the roadway and bridge over I-694. Access to businesses will be maintained via Hayward Avenue. Follow the posted detour route.
Landfall Access Map

Image: Landfall Access Map

fif

Image: 4th Street Closure Map

4th St.

Image: 4th Street Construction Map

Crews install rebar on the bus guideway between Century Avenue/Highway 120 and McKnight Road.

Image: Crews install rebar on the bus guideway between Century Avenue/Highway 120 and McKnight Road.  

Woodbury highlights

Ongoing:

  • Crews install planter beds along Bielenberg Drive between Hudson Road and Guider Drive.
  • Crews continue construction of the Queens Station.
  • Construction continues for the new Woodlane Park & Ride near the intersection of Woodlane Drive and Guider Drive.

Traffic impacts:

  • Guider Drive at Bielenberg Drive is reopened.
  • Lane closures in the work zones on Guider Drive, Bielenberg Drive, and Tamarack Road continue.
Updated Woodbury Construction Map

Image: Woodbury Construction Map

Construction noise and work hours reminder

Gold Line construction generally occurs between the hours of 7 a.m. and 7 p.m. You may notice early morning arrival of construction crew members and vehicles for site preparation. In addition, there are times when construction work does need to occur outside of these working hours. The project team does our best to notify area residents of these activities in advance, however, needs do come up in the field that require on the spot responsiveness and our construction crew needs flexibility to ensure the work gets completed.

We appreciate the community’s understanding as we continue to advance this work with the goal of bringing transit access and infrastructure improvements to the east metro.

Network Now

Network Now proposed plan available for public comment

Network Now is Metro Transit’s vision for transit service that best meets the needs of our region through 2027. This includes changes to transit service that is operated by Metro Transit in the communities along the Gold Line BRT Project corridor. The proposed regional plan will:

  • Expand service in our network by more than 35% to grow ridership
  • Improve coverage and mobility by expanding bus routes and Metro micro service
  • Redesign our express and commuter services to meet the travel needs of our region now

The plan has been released in full and is available for public comment until November 15. Visit the Network Now page to view the proposed plan, learn about upcoming public engagement events, and comment on the plans. https://www.metrotransit.org/network-now