METRO Gold Line BRT Construction Update:

 

June 2, 2023

Web: metrotransit.org/gold-line-construction

Construction Hotline: 651-602-1919

Email: goldline@metrotransit.org

Twitter: @GoldLineBRT

View an interactive map for specific construction location information.

Gold Line construction activities increase this week

Construction activities continue this week throughout the project area. Expect to see construction crews in St. Paul, Maplewood, Oakdale, and Woodbury. View a timelapse video of bridge construction in St. Paul and Woodbury.

 

2023 Construction Overview

2023 Construction Overview Map

 

Downtown St. Paul highlights

Ongoing:

  • Construction activities continue on the north side of 6th Street between Cedar and Minnesota Street. Next week crews will install foundations for the future station platform.

Traffic Impacts:

  • Lane closures on 6th Street between Cedar Street and Minnesota Street. The bus stop at Cedar Street will remain in service. The sidewalk adjacent to the work zone will be closed. Follow the posted pedestrian detour.

 

Gold Line Construction Map at 6th-Cedar

Image: Gold Line Construction Map at 6th-Cedar

 

East St. Paul highlights

 

Ongoing:

  • Near the intersection of Earl Street and Hudson Road, crews continue to excavate and construct retaining walls, install steel piles for retaining walls, and work on the Earl Street bridge.
  • Crews continue building a new bridge and backfilling excavated areas near the Etna Station site.
  • Near the intersection of Ruth Street and Old Hudson Road, crews continue to install steel piles and excavate for the new bridge, I-94 off-ramp, and bus guideway. Next week, crews begin installation of storm sewers, followed by installation of station foundations.
Crews construct a retaining wall in East St. Paul.

Image: Crews construct a retaining wall in East St. Paul.

 

Image: Map of Earl Street closure

Image: Map of Earl Street closure

 

Traffic Impacts:

  • The eastern half of Hudson Road between Cypress Street and Earl Street is closed for the next few weeks, including the Earl Street and Hudson Road intersection. Businesses on Hudson Road and Earl Street are accessible by sidewalks. Parking is available on Earl Street north of Hudson Road.
  • Earl Street is closed over I-94 between Hudson Road and Pacific Street. The closure continues until early summer 2023. Follow the posted detour route along Burns Avenue, Johnson Parkway, and 3rd Street.
  • Westbound I-94 shoulder closed and temporary ramp shift at Etna Street.
  • Westbound I-94 right lane and shoulder closed between Highway 61 and Mounds Boulevard. This closure continues through fall 2023.
  • Ruth Street is closed over I-94 and the westbound I-94 entrance ramp from Ruth Street is also closed. The closures will continue through fall 2023. Follow the posted detour route along Old Hudson Road, White Bear Avenue, and Suburban Avenue. Access to businesses is maintained on Ruth Street and Old Hudson Road via detour routes and sidewalks.

 

Ruth Street Closure

Image: Map of Ruth Street closure

 

St. Paul map

Image: St. Paul Map

 

Maplewood/Landfall/Oakdale highlights

 

Ongoing:

  • Crews install storm sewers and underground utilities over the next few weeks at Helmo Avenue south of 4th Street in Oakdale.
  • Private utility relocation work continues along 4th Street in Oakdale.
  • Crews continue pouring concrete for bridge foundations and constructing bridge abutments and walls on the north side of I-94, east of I-694.

Traffic impacts:

  • Starting Monday, June 5, Helmo Avenue closes south of 4th Street in Oakdale.
  • The Helmo Avenue and Hudson Boulevard intersection in Oakdale is closed.

 

Crews pour concrete into forms at the north Bielenberg bridge abutment in Oakdale.

Image: Crews pour concrete into forms at the north Bielenberg bridge abutment in Oakdale.

 

Oakdale-Landfall Construction Map

Image: Oakdale-Landfall Construction Map

 

Woodbury highlights

 

Traffic Impacts:

  • Bielenberg Drive between Hudson Road and Guider Drive is reduced to one lane in each direction on the east side.
  • The Hudson Road and Bielenberg Drive intersection is closed. Follow the posted detour route on Tamarack Road and Radio Drive. Access to businesses on Hudson Road and Bielenberg Drive remains open throughout construction.
Woodbury Construction Map

Image: Woodbury Construction Map

 

Ongoing:

  • Storm sewer and watermain installation continues moving south from the Hudson Road and Bielenberg Drive intersection.
  • Private utility relocation work continues along Bielenberg Drive in Woodbury.
Crews install storm sewers in Woodbury.

Image: Crews install storm sewers in Woodbury.

 

Nearby Projects:

  • MnDOT I-94 Pavement project
    • Ongoing lane closures and upcoming ramp closures at I-94 and Manning Avenue.