February 17, 2023
Web: metrotransit.org/gold-line-construction
Construction Hotline: 651-602-1919
Email: goldline@metrotransit.org
Twitter: @GoldLineBRT
View an interactive map for specific construction location information.
Construction activities continue in Woodbury for the new Bielenberg Drive bridge and near Etna Street in St. Paul. Timelapse video of bridge construction in St. Paul and Woodbury is available at: bit.ly/GL_construction
METRO Gold Line Construction Open Houses
Attend a public meeting this February/March to learn about 2023 Gold Line Construction. Stop by anytime throughout the meeting timeframe to talk with staff one-on-one about any of your questions, there will be no formal presentation. Information on the full line will be available at all open houses. Meeting details: metrotransit.org/gold-line-construction
Landfall/Oakdale/Woodbury Open House
Thursday, Feb. 23, 5:00 p.m. - 7:00 p.m.
Grace of God Lutheran Church
420 Hayward Ave. N., Oakdale
East St. Paul Open House
Tuesday, Feb, 28, 5:00 p.m. - 7:00 p.m.
Dayton's Bluff Elementary
262 Bates Ave., St. Paul
East St. Paul/Maplewood Open House
Wednesday, March 1, 5:00 p.m. - 7:00 p.m.
Eastern Heights Elementary
2001 Margaret St., St. Paul
Downtown St. Paul Open House
Tuesday, March 9, 11 a.m. - 1 p.m.
Metropolitan Council Chambers
390 Robert St. N., St. Paul
East St. Paul/Maplewood highlights
Ongoing:
- Crews continue building bridge foundations and piers near the Etna Station site.
- Pile driving continues near the Etna Station for the east bridge abutment and retaining wall. Pile driving activities are expected over the next few weeks.
- Crews concluded excavation of the stormwater pond near the intersection of Griffith Street and Wakefield Avenue. Work will continue as crews install a clay liner and maintain the area for staging throughout construction.
Traffic Impacts:
- Continued shoulder closure and temporary ramp shift at I-94 and Etna Street (as shown on map above).
Upcoming:
- Expect crews to install a clay liner next week at the stormwater pond area near the intersection of Griffith Street and Wakefield Avenue.
|
|
|
Photo: Pile driving for bridge construction continues near Etna Street.
Photo: Bridge abutment wall near Etna Street.
Photo: Crews tie rebar for wall construction near Etna Street.
Oakdale/Landfall/Woodbury highlights
Ongoing:
- Construction continues for the future BRT roadway, bridge abutments, and private utility work near the I-94/I-494/I-694 interchange area.
- Crews continue work in the I-94 center median between the I-494/I-694 interchange and Radio Drive, pouring concrete for bridge foundations and constructing bridge abutments at the north and south sides of I-94. Crews pour concrete for the south bridge abutment over the next few weeks.
- Private utility relocation work continues along Bielenberg Drive north of Tamarack Road and along 4th Street in Oakdale. Expect lane closures in this area.
- Building demolition is underway near the intersection of Hudson Boulevard N and Helmo Avenue N in Oakdale (see map above). Expect demolition to continue for the next few weeks.
Traffic Impacts:
- Expect median shoulder closures on eastbound and westbound I-94 between the I-494/I-694 interchange and Radio Drive throughout winter 2023. Intermittent eastbound left lane closures will occur in the coming weeks during off-peak hours.
- The Hudson Boulevard N and Helmo Avenue N intersection in Woodbury is expected to be closed starting Monday, Feb. 20 (see map above).
Nearby Projects:
|
|
|
Photo: Bridge foundation in Woodbury.
Photo: Crews install rebar at the south bridge abutment in Woodbury.
|