Web: GreenLineExt.org Twitter: @GreenLineExtMN Construction Hotline: 612-373-3933
Construction Photo: Bassett Creek Valley Station
 The Bassett Creek Valley LRT Station in Minneapolis continues to take shape. When complete the station will serve the Dunwoody College of Technology, the Walker Art Center and Minneapolis Sculpture Garden, and the Minneapolis neighbourhoods of Bryn Mawr, Harrison, Lowry Hill, and Kenwood. The station is conveniently close to the athletic fields and open space of Bryn Mawr Meadows.
Eden Prairie Highlights
Ongoing:
- Winter construction activity in Eden Prairie will be limited mostly to the area around SouthWest Station. Expect minimal updates to construction activities until spring 2023.
Visit our website for more details and visuals of construction activities in Eden Prairie.
Minnetonka Highlights
Ongoing:
- Crews continue to work on the Minnetonka-Hopkins LRT bridge. Expect minimal updates to construction activities until spring 2023.
Visit our website for more details and visuals of construction activities in Minnetonka.
Hopkins Highlights
Ongoing:
- The west sidewalk on Blake Road remains closed. Please use the sidewalk on the east side of Blake Road.
- The northeast and southwest sidewalks at Excelsior Boulevard and Jackson Avenue/ Milwaukee Street are closed through the winter.
- Expect minimal updates to construction activities until spring 2023.
Visit our website for more details and visuals of construction activities in Hopkins.
St. Louis Park Highlights
Ongoing:
- Winter construction activity in St. Louis Park will be intermittent.
- The east sidewalk along Wooddale Avenue remains closed. Please use the sidewalk on the west side of Wooddale Avenue.
Visit our website for more details and visuals of construction activities in St. Louis Park.
Minneapolis Highlights
Upcoming:
- The intersection of Dean Court and West 28th Street will be closed for about two months starting in late January to perform underground sewer utility work. Residents of the Cedar Isles Condominiums development will receive more detailed information about the timing of this closure once details are available.
- Royalston Avenue between 5th Avenue and Border Avenue has reopened to roadway traffic in a northbound-only condition.
Ongoing:
- Pumps and generators will run overnight periodically in various parts of the construction corridor, especially at the Kenilworth LRT tunnel site. Pumps are used to manage water, and generators are used to power the pumps as well as to power equipment that keeps pipes or other elements warm during freezing temperatures.
- Secant wall work is ongoing north of the West Lake Street Bridge.
- Cedar Lake Parkway is closed until spring 2023 to advance LRT tunnel construction. Pedestrian and bicycle access is maintained to the south via Depot Street and West 28th Street.
- The Cedar Lake Channel is closed to recreational use until spring 2023. The Kenilworth Lagoon is accessible from Lake of the Isles. This closure is necessary to remove and reconstruct historic retaining walls in the channel that were originally built under the Works Progress Administration.
- Pile-driving activities continue at Bryn Mawr Station through winter to construct retaining walls. Lane closures are in place on Wayzata Boulevard at the intersection of Penn Avenue.
- Construction at and around Bryn Mawr Station continues for work on the pedestrian bridge and station platform.
- Glenwood Avenue between Lyndale Avenue North and North 12th Street remains closed for construction of the LRT and two roadway bridges. See Minneapolis detour map.
- Bridge work near North 7th Street and North 6th Avenue continues.
Visit our website for more details and visuals of construction activities in Minneapolis
Trail Highlights
- Various trails within the Opus area are closed as crews advance many project elements. The Opus trails are anticipated to reopen in 2023.
- The Minnesota River Bluffs Trail between Shady Oak Road and 11th Avenue in Hopkins is anticipated to reopen in 2023.
- The Minnesota River Bluffs Trails between 11th Avenue and Excelsior Boulevard has reopened for local use.
- The South Cedar Lake LRT Trail between Excelsior Boulevard in Hopkins and Wooddale Avenue in St. Louis Park remains closed and is anticipated to reopen in 2024.
- The segment of the South Cedar Lake LRT Trail between Wooddale Avenue and Beltline Boulevard has reopened for local use. The South Cedar Lake LRT Trail between Beltline Boulevard and France Avenue in St. Louis Park remains closed and is anticipated to reopen in 2024.
- Temporary trails near Chowen Avenue and West Lake Street remain in place. For your safety and the safety of work crews, please follow signage for the temporary trail and stay clear of the work zone.
- The Kenilworth Trail will remain closed until the completion of LRT tunnel construction in 2025.
- The Luce Line Regional Trail bridge that crosses the BNSF rail corridor at Bryn Mawr Meadows Park is closed. A new bridge is being reconstructed to connect the new Bassett Creek Valley Station with the Park and is scheduled to reopen in 2025.
- The North Cedar Lake Trail east of Van White Memorial Boulevard is anticipated to reopen in 2025.
Project staff share the community’s desire to see the trails reopen as soon as possible. The project office will continue to work with the contractor to improve on these opening dates.
|