Wayzata Boulevard reconstruction update

Having trouble viewing this email? View it as a Web page.

wayzata boulevard reconstruction

County Road 112 in Long Lake and Orono

Final construction activities beginning soon

The second phase of Wayzata Boulevard (County Road 112) reconstruction is nearing completion. From now through July, crews will be working between Wolf Pointe Trail and Highway 12 on the following activities:

  • Paving the trail along westbound lanes to connect Wolf Pointe Trail and Luce Line Trail overpass.
  • Grading, paving and constructing medians along the east end between Orono Montessori school and Wayzata Boulevard West.
  • Constructing a pedestrian refuge island and crosswalk near Heather Lane to provide access to the trail.
  • Placing the final layer of asphalt between Wolf Pointe Trail and Highway 12 ramps.
  • Installing streetscape elements, placing sod and seeding.
  • Striping permanent roadway lines.

Ongoing activities

Trail construction progressing; paving expected tomorrow

In late May, construction of the new trail began along the northern half of Wayzata Boulevard between Wolf Pointe Trail and Luce Line Trail overpass. From the Luce Line Trail overpass, the trail connects to Willow Drive.

First, crews graded the new trail, which is made up of base layers of gravel. These layers are critical structural elements to provide a stable foundation needed for the pavement.

With grading completed, crews poured concrete pedestrian ramps at various intersections last week to prepare for trail paving. Paving will follow starting tomorrow, June 11. Weather permitting, we anticipate the work to take two days to complete.

Once completed, we will open up the trail for residents to enjoy.

Trail

This series of photos shows crews grading the trail and pouring concrete pedestrian ramps.

Construction activities at east end continue

Also in late May, crews began work on the center lane of Wayzata Boulevard between Orono Montessori school and Wayzata Boulevard West. 

Since then, underground utility lines were placed and grading work began for the new roadway and concrete median. This work is expected to be complete by the end of this week. Once complete, crews will begin grading work along the shoulder of westbound lanes in the same area.

This future work should not have any access impacts to nearby business driveways or side streets.

Staying safe

As you travel through the construction area, please allow for extra time to travel through the area, as delays can occur. For your safety and the safety of our crews, we ask that you slow down and follow the instructions of our crews and signage.

Contact

hennepin.us/countyroad112

612-543-4275

countyroad112@hennepin.us

Follow us

facebooktwitterinstagramyoutubelinked in
Hennepin County