Wayzata Boulevard reconstruction update

Having trouble viewing this email? View it as a Web page.

wayzata boulevard reconstruction

County Road 112 in Long Lake and Orono

Shoreline area work continues

This week, crews are continuing construction of the new roadway and trail along the shoreline area between Mill Street and Cemetery Road. 

Here is what you can expect this week along the shoreline area:

  • Grading the new trail and roadway with gravel
  • Pouring concrete for curbs and gutters
  • Preparing bases and conduits for new street lights
Curb and Gutter

Installation of new concrete curbs and gutters along the Long Lake shoreline is nearing completion.

Paving next week

Crews will return next week to pave between Mill Street and Cemetery Road. Weather permitting, paving is expected to take up to three days to complete.

Access impacts on Martha Lane during paving

Residents and businesses on Martha Lane will experience intermittent closures while crews pave through Martha Lane. The closure will occur on only one of the paving days and should last no more than two hours.

During the closures, people driving can use Mill Street to access businesses and homes. People walking, biking or rolling can continue to use the trail path connecting Mill Street and Martha Lane.

Sidewalk work at Lake Street intersection

On Friday, June 29, crews are scheduled to pour colored concrete at the pedestrian curb ramp on the northwest corner of the Lake Street intersection.

First, forms will be constructed to outline where the pedestrian ramp will be poured. Then, crews will pour the concrete and let it cure.

Weather permitting, the work should only take around two days. One day is needed for the concrete work. An additional day is needed for the concrete to cure, or strengthen for regular use. 

During concrete work, people walking, running and rolling will need to use adjacent sidewalks to get around.

Excavations continue

Between Old Long Lake Road and Luce Line Trail overpass

Crews are continuing excavation work along the northern half of Wayzata Boulevard between Old Long Lake Road and the Luce Line Trail overpass.

This work will cause intermittent traffic impacts this week, as large trucks will be hauling soil in and out of the work areas. Additional crews will be on site to guide traffic during the work.

Weather permitting, excavation work is expected to be complete by end of next week.

Shoulder strengthening work begins late next week

Between Birches on the Lake and Old Long Lake Road

Starting late next week, crews will be doing shoulder strengthening work along the northern half of Wayzata Boulevard between Birches on the Lake and Old Long Lake Road.

The shoulder work will provide extra strength to support traffic when traffic shifts to the northern half of Wayzata Boulevard in mid-July. Weather permitting, we anticipate this work to take up to three days to complete.

While this will not impact through traffic, there will be brief closures to driveways along the northern half of Wayzata Boulevard. Impacted residents and businesses will be notified. People will still have access to Birches on the Lake during our work.

Visiting local businesses

Please remember you can still access all businesses throughout Wayzata Boulevard. Plan ahead and allow yourself extra time to reach your destination.

If you have any concerns about how to access a local business, please call the business you are visiting or the project at 612-543-4275 or email at countyroad112@hennepin.us. 

Staying safe

It is important to follow posted speed limits and construction signs to help you navigate through work zone, including evenings and weekends. Please allow yourself some extra time to reach destinations in the area.

Contact

hennepin.us/countyroad112

612-543-4275

countyroad112@hennepin.us

Follow us

facebooktwitterinstagramyoutubelinked in
Hennepin County