Media contact: Kyle Mianulli, Communications, 612-596-9875
Starting Monday, May 8, Portland Avenue (County Road 35) and Cedar Avenue (County Road 152) in Minneapolis will close between 28th Street and Lake Street as reconstruction of the two bridges over the Midtown Greenway begins.
Both bridges will be closed to all road traffic for the duration of the project. Work is expected to last one construction season and be significantly complete with the road reopened by December this year. See detour information below.
Greenway trail closure at Cedar Avenue expected May 15
Starting Monday, May 15, the greenway trail is expected to
close at Cedar Avenue as crews demolish the bridge. This work is expected to
last several days with the trail reopened by that weekend. See detour
information below.
Once demolition of the Cedar Avenue bridge is complete and
the trail is reopened, crews will begin demolition of the Portland Avenue
bridge and the trail will be closed at that location for approximately five
days. The Portland Avenue closure is expected to happen Monday, May 22.
Detour information
Portland Avenue detours
Road (motor vehicles)
- Franklin Avenue (County Road 5)
- Chicago Avenue South
- Lake Street (County Road 3)
Road (bikes)
- East 28th Street
- 4th Avenue South
- East 32nd Street
Trail
- Park Avenue
- East 28th Street
- 5th Avenue South
Cedar Avenue detours
Road
- Lake Street (County Road 3)
- Hiawatha Avenue (Highway 55)
Trail
- 18th Avenue South
- East 28th Street
More information: www.hennepin.us/greenwaybridges
– 30 –
Look for more news on the Hennepin County website at www.hennepin.us/news.