It has been a busy construction season for the crews on the project. We
thought you would appreciate learning more about a few key construction accomplishments and getting an updated timeline for the work that
remains.
Here are the details:
From Excelsior Boulevard to Mainstreet, crews are completing the final
portion of the underground work (water, storm and sanitary mains). We
anticipate having Shady Oak Road complete from Excelsior
Boulevard to Highway 7 in time for winter, with the exception of the final layer pavement
to be placed next year.
The Hopkins city streets (2nd Street, 21st Avenue and West Park Road)
are complete. The final layer of pavement will be placed on 21st Avenue before
winter. 2nd Street and West Park Road had the final layer of pavement placed last
fall.
The cul de sac off Lake Street Extension cannot be completed until the
traffic switch onto the new alignment at Highway 7. This area and the
North Service Drive will be the last items completed.
The portion of Shady Oak Road north of Highway 7 should be open on the new alignment this fall.
 View of new lanes being constructed
|