Environmental review project notices
EQB publishes environmental review notices provided by responsible governmental units. For more information on a project undergoing environmental review, click on the individual project links below. You can also find information about active projects in your community on the Environmental Review Projects Interactive Map.
*This project notice was previously published in the August 11, 2026 EQB Monitor with the end of comment period listed as September 10. The comment period has been extended per the below.
Location (city/township; county): Fridley; Anoka, Hennepin Process: EAW Step: EAW available End of comment period: October 12, 2026
Project description: The Twin Cities' Metropolitan Council Environmental Services (MCES) proposes to decommission an aging wastewater lift station and construct a new, larger lift station in the northwest metro area to meet growing capacity needs. Project improvements will include construction of a new lift station along the Mississippi River in Fridley, decommissioning of the existing lift station across the Mississippi River in Brooklyn Park, and rehabilitation of pipes crossing the Mississippi River (Project).
Link to public documents: MCES L32A Lift Station EAW
Location of public documents: MPCA, 520 Lafayette Rd N, Saint Paul, MN 55155
Responsible governmental unit and contact: Minnesota Pollution Control Agency, Doree Husnik, 651-757-2374
Location (city/township; county): Saint Paul; Ramsey Process: EAW Step: EAW available End of comment period: October 8, 2026
Project description: Wold Engineers and Architects is preparing plans and specifications for demolition of the Centennial Office Building at 658 Cedar St, Saint Paul, MN. The project includes full structure removal, including foundations and utilities serving the site. Municipal utilities removal will comply with City requirements to remove the service to the main. After demolition and site fill, the area will be converted into an open landscaped green space with an infiltration area. Work is scheduled for 2028. Centennial Office Building Demolition project link provided by RGU
Location of public documents: Minnesota Department of Administration, Office of State Procurement, 112 Administration Building, Saint Paul, MN 55155
Responsible governmental unit and contact: Minnesota Department of Administration, Stacie Christensen, 651-201-2500
Location (city/township; county): Morris; Stevens Process: EAW Step: EIS need decision
Responsible governmental unit decision: Negative (no EIS ordered) Responsible governmental unit record of decision date: August 25, 2026
Project description: The Pomme de Terre River Association is proposing a multi-component project to restore the hydrology and natural habitats of the Pomme de Terre River through Crissy Lake in the City of Morris, Minnesota. The project components include removal of the Crissy Lake Dam, installation of two rock arch rapids to replace the existing structure, and channel restoration extending from the existing dam to the upstream end of Crissy Lake. Crissy Lake Dam Modifications EAW project link provided by RGU
Location of public documents: DNR, 500 Lafayette Rd, St Paul, MN 55155
Responsible governmental unit and contact: Minnesota Department of Natural Resources, Environmental Review Unit, Yvette Gault, 651-259-5516
Location (city/township; county): Fall Lake Township; Lake Process: EAW Step: EIS need decision
Responsible governmental unit decision: Negative (no EIS ordered) Responsible governmental unit record of decision date: August 25, 2026
Project description: Leisure Hotels and Resorts is proposing construction of an update to and expansion of the existing Silver Rapids Lodge resort site located in Fall Lake Township, Lake County, Minnesota. The project will include demolition of a functionally obsolete lodge, the construction of a new lodge, 44 new cabins, as well as other amenities.
Location of public documents: Lake County Department of Environmental Services, 601 3rd Ave, Two Harbors, MN 55616
Responsible governmental unit and contact: Lake County, Bryr Ludington, 218-834-8327
Location (city/township; county): Arden Hills; Ramsey Process: EIS Step: EIS preparation notice
Project description: Maplewood Development, Inc. proposes a 62-acre, 972,200 square foot warehouse/distribution/office park development near the corner of County Road I and Fairview Avenue, on property formerly associated with the Twin Cities Army Ammunition Plant (TCAAP) operations, in Arden Hills, Minnesota. The Hillview Business Park development requires the preparation of an Environmental Impact Study (EIS) to be prepared after this scoping EAW. The project will demolish existing abandoned buildings, undertake environmental remediation, and construct several warehouse/distribution buildings with associated utilities and access on the site.
Summary of scoping decision: Public review and comment on the Draft SDD was completed in accordance with Minnesota Rules part 4410.2100. The Draft SDD and Scoping EAW were published in the EQB Monitor for a comment period on June 16, 2026. The public comment scoping period ended on July 16, 2026. Consistent with Minnesota Rules part 4410.1500, notification of completion of the Draft SDD and Scoping EAW were published on the City's website and a notice of availability was published in the Saint Paul Pioneer Press on June 17, 2026. The RGU considered the substantive scoping comments received and developed this Final SDD. Following consideration of written comments and testimony received at the August 24, 2026, City Council meeting, the Final SDD was presented to the City Council for adoption. The City Council adopts the Final Scoping Decision Document for the EIS to be prepared for the Hillview Business Park Project and authorizes the preparation of the Draft EIS. Hillview Business Park project link provided by RGU
Location of public documents: Arden Hills City Hall, 1245 W Highway 96, Arden Hills, MN 55112
Responsible governmental unit and contact: City of Arden Hills, Jake Reilly, 651-792-7824
Location (city/township; county): Brooklyn Park; Hennepin Process: Large AUAR Step: Draft AUAR End of comment period: October 8, 2026
Project description: The Study Area is located in Section 6 and 7, Township 119N, Range 21W in Brooklyn Park, Hennepin County, Minnesota. The proposed development scenario would include the development of the Study Area including residential, commercial, transit-oriented development, and biotechnology development including research, office, production, and manufacturing space. The development scenario would also include the construction of infrastructure including roads and utilities. Brooklyn Park NW Growth Area Plan project link provided by RGU
Location of public documents: City Hall, 5200 85th Ave. N., Brooklyn Park, MN 55443
Responsible governmental unit and contact: City of Brooklyn Park, Erin McDermott, 763-493-8082
Location (city/township; county): Lakeville; Dakota Process: Large AUAR Step: AUAR adoption
Responsible governmental unit decision: Adequate Responsible governmental unit record of decision date: August 17, 2026
Project description: The Southwest Study Area ("AUAR Area") includes twenty-one (21) parcels that comprise approximately 390.4 acres in Lakeville, Dakota County, Minnesota. The AUAR Area is generally located south of County State Aid Highway (CSAH) 70/210th St W, west of Interstate 35 (I-35), and east of the City of Credit River, Scott County. Parts of the AUAR Area have historically been in agricultural use, several parcels are currently rural residential land use, and one parcel is currently undeveloped. Artemis Development Company (“Proposer”) is proposing to phase development within the AUAR Area to convert the existing land into a master planned residential and commercial development that may include institutional uses including a school over the next several years.
Location of public documents: City of Lakeville City Hall, 20195 Holyoke Avenue, Lakeville, MN 55044
Responsible governmental unit and contact: City of Lakeville, Tina Goodroad, 952-985-4421
Location: Pine Island, Goodhue Process: Alternative review End of comment period: September 25, 2026
Notice title: NOTICE OF PUBLIC HEARINGS AND AVAILABILITY OF DRAFT PERMIT Notice description: PLEASE TAKE NOTICE that the Minnesota Public Utilities Commission will hold public hearings on the route permit application of Northern States Power Company, doing business as Xcel Energy, and Echo Zone LLC, a subsidiary of Google LLC for the North Rochester to Skyway 345 kilovolt Transmission Line Project.
Project description: Northern States Power Company, doing business as Xcel Energy, and Echo Zone LLC, a subsidiary of Google LLC (Applicants) proposed to construct an approximately 1.2-mile double circuit 345 kilovolt (kV) transmission line that would connect Xcel Energy's North Rochester Substation to four new substation facilities at the proposed Pine Island Industrial Planned Unit Development (Project Skyway) site. The Applicants also proposed to expand the existing North Rochester Substation, currently on a footprint of 10 acres, by approximately 11.3 acres. The transmission line and North Rochester Substation expansion (North Rochester to Skyway HVTL Project) will be owned and operated by Xcel Energy, and the four Project Skyway substations will be owned and operated by Echo Zone LLC. Project information is located in the Commission’s eDocket system via eDocket Number 26-135.
Location of public documents: Minnesota Public Utilities Commission, 121 7th Place East, Saint Paul, MN 55101
First public meeting date, time, location: September 14, 2026, 6:00 p.m., Pine Island American Legion, 108 1st Ave SE, Pine Island, MN 55963 First public meeting additional details: The hearing ends when all present attendees have commented or at 8:00 p.m., whichever comes first. Please arrive at the start time to ensure participation. If any reasonable accommodation is needed to enable you to fully participate in these hearings, please contact the Commission at 651-296-0406 or 1-800-657-3782 at least one week in advance of the hearing. To find out if a hearing is canceled due to bad weather or another reason, call 1-855-731-6208 or visit the Commission's website.
Second public meeting date, time, location: September 15, 2026, 6:00 p.m., Online meeting Second public meeting virtual link: Join online meeting Second public meeting additional details: Webinar Number: 2486 478 6456 Webinar Password: MnPUC! (667820 when dialing from a phone) Join by Phone: 1-415-655-0003 Access Code: 2486 478 6456 If you are joining the hearing via WebEx and would like to ask a question or make a comment during the designated portion of the hearing, use the raised-hand function or the chat function to send a message to the hearing moderator. If you are joining the hearing by phone, press *3 on your phone. When it is your turn to speak, your line will be unmuted, and you will be able to ask questions and provide comments. Additional information and instructions are available at the Commission's meetings webpage.
Responsible governmental unit and contact: Minnesota Public Utilities Commission, Sam Weaver, 651-539-1531
Location: Hermantown, Saint Louis Process: Alternative review End of comment period: September 22, 2026
Notice title: Environmental Assessment Notice description: City of Hermantown is the local governmental unit responsible for approval of the proposed 230 kilovolt (kV) transmission lines (Project) that will connect to Minnesota Power's existing Arrowhead 230 kV Substation and to the customer's facility within the municipal boundaries of the City of Hermantown, Minnesota. The comment deadline is September 22, 2026 and comments can be submitted to comments@stlouiscounty230kv.com.
Project description: Minnesota Power requested local review, pursuant to Minn. Stat. § 216I.08 for the Project. The City of Hermantown has prepared an Environmental Assessment ("EA") for the proposed Project as required under Minn. Stat. § 216I.08, subd. 4 to support its decision and to evaluate potential impacts associated with the Project. Minnesota Power proposes to construction two parallel 230 kilovolt (kV) transmission lines that will connect to Minnesota Power's existing Arrowhead 230 kV Substation and to the customer's facility within the municipal boundaries of the City of Hermantown, Minnesota. Project information is located in the Public Utilities Commission's eDocket system via eDocket Number 26-269.
Location of public documents: City of Hermantown, 5105 Maple Grove Road, Hermantown, MN 55811
Responsible governmental unit and contact: City of Hermantown, Eric Johnson, 218-729-3618
Fish kill reports
Minnesota Duty Officer reports pertaining to fish kills are summarized in the following table, in accordance with 103G.216, REPORTING FISH KILLS IN PUBLIC WATERS, Subd. 2 Reporting Requirement. These reports were received via the Minnesota Duty Officer prior to the submission deadline for this edition of the EQB Monitor. They represent the raw data/information provided by callers. For more information regarding fish kills in Minnesota see the Department of Natural Resources. Call the Minnesota Duty Officer at 651‐649‐5451 or 800‐422‐0798 to report fish kills.
|
Date
|
Location
|
County
|
Waterbody
|
Species
|
Count
|
|
8/26/2026
|
Inver Grove Heights
|
Dakota
|
Simley Lake
|
Unspecified
|
50
|
|
8/29/2026
|
Sauk Centre
|
Stearns
|
Sauk Lake
|
Carp, Sucker
|
100
|
|
8/29/2026
|
Sauk Centre
|
Stearns
|
Sauk River
|
Sunfish, perch, carp, Walleye
|
75
|
|
8/31/2026
|
Sauk Centre
|
Stearns
|
Sauk River
|
Unknown
|
200
|
Submit a notice to the EQB Monitor
The EQB Monitor is a weekly publication announcing environmental review documents, public comment periods and other actions of the Environmental Quality Board. The EQB Monitor is published every Tuesday at noon. Submissions to the EQB Monitor are due by 4:00 p.m. on the Tuesday one week prior to the intended publication date. Please see the EQB Monitor schedule for more details.
To submit a notice for publication:
Questions? Contact EQB by phone at 651-757-2873 or email us at EQB.Monitor@state.mn.us.
For more information on environmental review, please visit the EQB website or contact us at env.review@state.mn.us.
|