ITS/TMS design resources
 The following changes have been made to various MnDOT ITS/TMS design technical resources at mndot.gov/freeway-operations/its.html.
- ITS/TMS Design Quick Reference Guide – revised Oct. 29, 2026
- Page 3:
- Replaced the COPPER CONDUCTOR CABLE/AMPERAGE CAPACITY section with ELECTRICAL WIRE CHARACTERISTICS, and revised Table 3-1 from the ITS/TMS Design Manual
- Circuit breaker sizing: updated explanation
- Page 4:
- Typical branch conductors: updated applicable distances for several cables based on updated tables on pages 6 & 7
- Voltage drops: updated preferred % drop to 4% for branch and feeder circuits
- Pages 5 & 6: updated the max preferred amperage tables for 4% voltage drop, and based on the updated values in Table 3-1
- Page 7: updated fiber optics schematics snip
- Page 11:
- Mulch material type 9 areas: split out Light Foundation Design E Modified
- Detail sheets order: split out CCTV Cabinet Installation from Ramp Control Signal Foundation Installation
- ITS/TMS Sample Plan - revised Oct. 29, 2026
- Sheet 12:
- Added proposed signal system mounted cameras (notes 54 & 55) to cover that example
- Updated various details (see detail sheets section below)
- Detail sheets
- TMS sediment & erosion control detail – revised Oct. 26, 2026
- Added sidewalks to pole foundation detail
- Mulch material type 9 installation – revised Oct. 22, 2026
- Separated Light Foundation Design E Modified from CCTV Foundation
- Non-intrusive detection pole installation – revised Oct. 26, 2026
- Modified several notes, revised sidewalk placement
- CCTV cabinet installation – revised Oct. 27, 2026
- Updated a few notes for clarity/grammar
|
|