 2026 construction: Highway 28 Morris to Starbuck
|
|
Construction progress
Between Cyrus and Starbuck, crews continue turf establishment and other cleanup. Final striping will be done later, once paving in Cyrus is complete. Local traffic should continue to drive with caution between Cyrus and Starbuck and always obey traffic control.
Concrete crews have started installing curb and gutter in Phase 2 in Cyrus, and concrete work is ongoing as the sidewalks, ramps and boulevards are poured. Paving crews are expected to be in Cyrus the first week of September to pave the roadway.
 Concrete curb and gutter installed along Highway 28 in Cyrus
 Crews have poured portions of sidewalk in Cyrus
 Other local traffic safety reminders:
- This is an active work zone, even in areas where workers aren't present. Please slow down, and travel with extreme caution and care.
- Be alert for changing conditions, such as uneven, rough and/or gravel surfaces
- Watch for workers, trucks hauling, and slow-moving heavy equipment
The highway is closed to thru-traffic. If you don't have a destination along the roadway, please follow the signed detour route. For access to Cyrus, follow the detour and from County Road 18 use County Road 3 to enter from the south.
 Upcoming schedule
- Finish turf work between Cyrus and Starbuck
- Continue installing sidewalks in Phase 1 in Cyrus
- Install curb and gutter in Phase 2 in Cyrus
- Final striping from Starbuck to Cyrus
For more information, please visit the project website.
|
|