D1 - Hwy 61 & London Road: 2026-2027 construction
Current and upcoming work
- Work at 26th Ave E roundabout continues. Earthwork and storm sewer placement is now complete. Concrete curb and gutter will be placed this week with paving next week.
- From 41st Ave E to 60th Ave E:
-
Traffic switch complete with traffic traveling on inland side
-
Sod watering activities will slow traffic from 10 - 11:30 a.m. for the rest of this week
-
Removals of driveways and curb will continue. Notifications will be in person and flyer will be given when the 6 day closure for concrete happens
-
Storm sewer installation will take place over the next two weeks
Traffic control
-
North of 40th Ave E, London Road is only open to northbound traffic. Southbound traffic is detoured on to Superior St to 40th Ave E.
-
The southbound truck detour has traffic continue on Superior St to 21st Ave E.
-
There is a hard closure of London Road just past the business accesses before 26th Ave E when heading north/east. There is also a hard closure of 26th Ave E just up the hill from London Road.
-
All north/east I-35 traffic is on a bypass to continue on London Road. There is no access to 26th Ave E from I-35 or London Road.
- Traffic impacts are expected through the fall.
Contact Us
For specific questions, please contact project staff via email at London.Road.DOT@state.mn.us.
mndot.gov/d1/projects/londonroad
|
|
If you need an ASL, or a foreign language interpreter, or documents in an alternative format please contact Janet Miller at 651-366-4720 (711 or 1-800-627-3529 for MN Relay). If you need any other reasonable accommodation to participate, please email your request to ADArequest.dot@state.mn.us. |
|
|
|