It's been an exciting summer of progress on the 11th Street underpass! In Stage 3 along Center Avenue, crews have been getting the roadway rebuilt after completing all of the underground work and final utility hook ups. Concrete paving started in July, beginning with 11th Street underneath the two bridges, followed by sidewalk pours along this section. On Center Avenue, crews have paved the eastbound and westbound lanes, and will be hand-pouring the gaps to tie together 11th and Center Avenue. Sidewalks along Center Avenue will be poured next. Over the next month, crews will be working on the final connection, paving between 11th and 10th Streets, to tie into the city of Moorhead's project between 8th and 10th Street.
While a lot of those big milestones are underway, there has been a lot of other smaller touches happening—bridge painting is done, railings are being installed, signals are going in as the sections finish. As progress continues, you'll see other cleanup happening throughout the project area, lighting installations and final striping to come, too.
As always, we appreciate your patience and understanding as the project progresses toward completion, which remains on schedule for this fall!
All construction activities, schedules and traffic impacts are weather dependent.
Check out the photos below that show the progression of construction since July!
 From July 2026, crews work at the intersection of Center Avenue and 10th Street.
 From July 2026, view of Stage 3 along Center Avenue and 11th Street, prior to paving starting
 From early August 2026, crews paved the driving lanes underneath the two bridges on 11th Street
 From early August 2026, crews rebuild the intersection of Center Avenue and 10th Street
 From late August 2026, paving starts on Center Avenue. Crews have since completed both eastbound and westbound driving lanes, and will start hand-pouring the gaps.
 Over the next month, crews will pave between 11th Street and 10th Street, and install sidewalks throughout the project.
Join us at our final "Coffee & Construction" monthly meeting on Sept. 15 at 9 a.m., at the Hjemkomst Center. These meetings are held the third Tuesday of each month, and this will be our last one for the project! At these meetings you can expect a short overview on progress from the contractor and MnDOT, and the opportunity for anyone to ask questions or share concerns.
We appreciate the consistent attendance to these meetings over the last three years. Thank you for your commitment to staying engaged and informed.
-
Moorhead businesses are open during construction! If your destination falls within/near the work zone or along the detour routes, please check in with the business to determine the best route there.
-
Never enter an area that's blocked by barriers or cones. It is not safe to drive, walk or bike around barricades, even in areas where workers aren't present or active. Those boundaries are set up for your safety. There are signed detours installed for both motorists and pedestrians. Please use those routes.
Please report any issues to the 11th Street Underpass hotline number at 218-292-8779.
For more information about this project, visit the project website at mndot.gov/d4/projects/moorhead11thstunderpass.
|