On Friday, June 19 and Monday, June 22, weather permitting, the bridge beams will be set over westbound I-94! Interstate traffic was switched to head-to-head near the interchange to give crews the space they need for this work.
Once the beams are in place, crews will start on the bridge decking! After the Fourth of July holiday, they'll switch the head-to-head traffic to the westbound side and set beams over the eastbound lanes. We appreciate the traveling public's patience during these changing traffic patterns as the project progresses.
On Highway 210, crews are finishing up the underground work west of the bridge, and grading the roadway, ramps and roundabout locations, and those same operations are picking up on the east side of the bridge.
I-94 traffic for Exit 54 should continue to use the detour on County Road 1 and Tower Road (Exit 55). Please travel with care.
Upcoming schedule
- Install bridge beams over westbound I-94 - Friday and Monday!
- Begin bridge decking
- Continue grading on Highway 210 and ramps
- Continue installing underground work, construct roundabout at the eastbound I-94 on- and off-ramps
Completed work
- Construct bridge structure elements (piers, pier caps, west and east abutments)
- Storm sewer and culverts installed from Redwood Lane to the west
- Grading of eastbound I-94 off-ramp
 Culvert installation at the future location of the eastbound I-94 on-ramp
 Crews pour the west abutment at the Highway 210/I-94 interchange bridge
 Center pier columns for the new bridge
For more information about this project, visit the project website.
All construction activities and traffic impacts are weather dependent and subject to change. MnDOT urges motorists to always be attentive, drive with caution, slow down in work zones where workers are present, and never enter an area that's blocked by barriers or cones.

|