  Highway 11 Roseau to Warroad project limits
 Centerline culvert replacements are well underway on the east end of the project
 Highway 11 Warroad ridge area-shoulder widening
 Reclaiming Highway 11 on the east end of the project limits
 Realignment of Ridge Road/CR 46 to Highway 11
Highway 11 Roseau to Warroad: June 4 update
Crews continue to make steady progress on the Highway 11 Roseau‑to‑Warroad project. Here is what crews are currently working on and what to expect next:
- Centerline culvert replacements on the east segment of the project (Stage 2) is well underway, with roughly half of the culverts now completed.
- Widening work has begun on the Warroad ridge area (Stage 3) and will continue over the next couple of weeks.
- Reclaiming operations have started on the east end of the project and will move west toward Roseau County Road 13.
- *Photos taken June 4
Traffic Impact
Highway 313 and Roseau County Road 13 remain the designated detour route for through traffic between Roseau and Warroad. Highway 11 is open to local traffic only.
Nearby project:
Construction on the Highway 11 Warroad River bridge will resume on June 8. This two‑year project includes replacing the bridge over the Warroad River.
Work began in May 2025 with replacement of the west side of the bridge. During the 2026 construction season, crews will replace the east side. The project is expected to be completed by November, weather permitting.
Motorists will encounter single‑lane traffic on the bridge controlled by temporary signals. A truck detour will be in place using Roseau County Roads 9 and 12.
Highway 11 Improvement Project - MnDOT
Work zone safety reminders
- Slow down when approaching every work zone
- Never enter a roadway that has been blocked with barriers or cones
- Stay alert; watch for workers and slow-moving equipment
- Obey posted speed limits. Fine for a violation in a work zone is $300
- Minimize distractions behind the wheel
- Be patient; expect delays, especially during peak travel times
For real-time traffic and travel information in Minnesota, visit www.511mn.org or get the free smartphone app at Google Play or the App Store.
 Stage 3: Reconstruct the "ridge" area with right-turn lanes and center left-turn lane
|