D3 - Hwy 95 in Cambridge: 2026-2027 construction
 Let the improvements begin!
Roadwork on Hwy 95 is about to start, and we're excited to kick things off. Beginning Mon, April 20, we'll launch the first year of a two‑year project to rebuild and improve the highway between Fern St. and Fillmore St. Work will happen in segments over the next two seasons, beginning on the west end at Fern St. and moving east toward Main St. Then in 2027, crews will be back to finish the final segment from west of Main St to east of Fillmore St.
 Hwy 95—Cambridge. Select image to visit the project web page.
What to expect April 20 to mid-October 2026
April 20 to early May
You may see short‑term lane or shoulder closures east of CR 70 while crews set up the work zone and build a crossover connection to Second Ave. SW. Delays should be minor.
Early May to late July
Hwy 95 will close between Fern St. and Dellwood St. while we rebuild the road and replace utilities.
Detours:
- Westbound traffic will use Cypress St. S and Second Ave. SW
- Eastbound traffic will use Second Ave. SW and Birch St. S
 Hwy 95 Fern to Dellwood detour map. Select image to enlarge.
Late July to mid-October
Crews will move east as Hwy 95 closes from east of Dellwood St. to west of Main St.
Detour for both directions:
- Use Dellwood St. S, 11th Ave. SE and Garfield St. S
 Hwy 95 Dellwood to Main detour map. Select image to enlarge.
 |
|
Please note: Construction is like Minnesota weather—changes or updates to these details could change, but we'll keep you posted along the way. |
More about this project
This two‑year, $18 million project will rebuild and expand Hwy 95 in Cambridge to improve traffic flow, increase capacity, and enhance safety for all users. When complete in fall 2027, the upgraded roadway, improved sidewalks and accesses and updated city utilities will provide a smoother, more reliable route with reduced long‑term maintenance needs.
|