Week 26 progress
Paving crews are here and they have the first two lifts (layers) of pavement done in Stage 3A-B on Highway 108 west, and are now working on the second lift on Highway 59, County Road 9 and Pete Lane. Then comes the final lift in all of Stage 2C on Highway 59, north of Fifth Avenue NE. You will encounter delays while that work is being done under traffic. Please obey the flaggers!
On the west side of town, the crew has milled on Highway 108 west, west of Third Avenue. When they finish up on Highway 59, the crew will jump back to Highway 108 west to finish paving throughout all of Stage 3A-C.
Striping and sign installation will follow.
 Crews pave the first lift (layer) of pavement on Pete Lane
 Paving operations continued after dusk as crews paved the first lift at the intersection of Highway 59 and County Road 9
 First two lifts are done on Highway 108 west. Final paving in Stage 3A-C on Highway 108 west will follow the completion of paving on Highway 59.
 Crews milled the west end of Highway 108 west, getting it ready for the final paving through all of Stage 3A-C
There are several ways you can find information or get your questions answered:
All construction activities and traffic impacts are weather dependent and subject to change. MnDOT urges motorists to always be attentive, drive with caution, slow down in work zones where workers are present, and never enter an area that's blocked by barriers or cones.
|