Highway 11 Warroad Construction: October 24
What's happening this week?
Oct. 20 -25
-
Traffic impacts: Truck detour in place. Single lane traffic with temporary lights at Warroad River bridge. See detour maps.
-
Bridge project –Paving approaches, pouring pilasters and edge rail.
- MnDOT is planning to open the bridge to traffic Nov. 7, weather permitting.
About the project:
MnDOT, in collaboration with Roseau County and the City of Warroad, plans to reconstruct Highway 11 between County Road 5 and Highway 313/Cedar Avenue NW and Cedar Avenue NW between Highway 11 and Lake Street.
Construction is scheduled to take place in 2024-2026.
These roadways are in need of long-term improvements to address aging infrastructure, safety, and access issues. This project will resurface deteriorating pavement, replace storm sewer, and incorporate landscaping along the project area.
2024: Resurface Hwy 11 south of the bridge and Cedar Ave. Begin Hwy 11/313 roundabout.
2025: Construct Highway 11/313 roundabout. Begin half of the bridge construction.
2026: Continue other half of the bridge construction.
The bridge will be constructed in 2025 and 2026. The bridge will remain open during the winter months.
How about a roundabout?
Traffic impacts:
  The truck detour is in place for the duration of the project.