 Stage 3 of the roundabout construction is underway. Highway 313 motorists will detour using Gladys, Main St. and CR 74. See detour map. Highway 11 east, west and south legs of the roundabout are open to traffic. Motorists are encouraged to use additional caution in the work zone. Hwy 313 leg of the roundabout is expected to be open to traffic on September 17, weather permitting.
Highway 11 Warroad Construction: September 12
What's happening this week?
September 8-13
-
Traffic impacts: Truck detour in place. Highway 313 detour in place. Single lane traffic with temporary lights at Warroad River bridge. See detour maps.
-
Bridge project –Preparing north and south abutments
-
Roundabout project (Stage 3) –Paving
What's happening next week?
September 15-20
-
Traffic impacts: Truck detour in place. Highway 313 detour in place. Single lane traffic with temporary lights at Warroad River bridge. See detour maps.
-
Bridge project – Begin setting beams for new bridge
-
Roundabout project (Stage 3) –Complete paving and open north leg (Hwy 313) to traffic by September 17, weather permitting. Striping will be completed under traffic
About the project:
MnDOT, in collaboration with Roseau County and the City of Warroad, plans to reconstruct Highway 11 between County Road 5 and Highway 313/Cedar Avenue NW and Cedar Avenue NW between Highway 11 and Lake Street.
Construction is scheduled to take place in 2024-2026.
These roadways are in need of long-term improvements to address aging infrastructure, safety, and access issues. This project will resurface deteriorating pavement, replace storm sewer, and incorporate landscaping along the project area.
2024: Resurface Hwy 11 south of the bridge and Cedar Ave. Begin Hwy 11/313 roundabout.
2025: Construct Highway 11/313 roundabout. Begin half of the bridge construction.
2026: Continue other half of the bridge construction.
The bridge will be constructed in 2025 and 2026. The bridge will remain open during the winter months.
How about a roundabout?
Traffic impacts:
 Stage 3: Construct north leg of the roundabout. Hwy 313 will be closed during this stage. See detour map.
  The truck detour is in place for the duration of the project. The Hwy 313 detour will only be in place during Stage 3 of the project.
www.511mn.org
Visit: mndot.gov/d2/projects/hwy11-warroad
|