 Stage 3 of the roundabout construction is underway. Highway 313 motorists will detour using Gladys, Main St. and CR 74. See detour map. Highway 11 east, west and south legs of the roundabout are open to traffic. Motorists are encouraged to use additional caution in the work zone.
Highway 11 Warroad Construction: September 5
What's happening this week?
September 2-6
-
Traffic impacts: Truck detour in place. Highway 313 detour in place. Single lane traffic with temporary lights at Warroad River bridge. See detour maps.
-
Bridge project –Crews continued working on south abutment. Pile driving and rip-rap placement was completed.
-
Roundabout project (Stage 3) –Concrete was poured on the Hwy 313 leg (north) of the roundabout. Sidewalks and ADA work also finished on north side.
What's happening next week?
September 8-13
-
Traffic impacts: Truck detour in place. Highway 313 detour in place. Single lane traffic with temporary lights at Warroad River bridge. See detour maps.
-
Bridge project – Crews will begin installing falsework for south abutment and pour concrete in the same location
-
Roundabout project (Stage 3) –Final grading and preparation for pavement. Paving will start end of the week and progress into the following week.
About the project:
MnDOT, in collaboration with Roseau County and the City of Warroad, plans to reconstruct Highway 11 between County Road 5 and Highway 313/Cedar Avenue NW and Cedar Avenue NW between Highway 11 and Lake Street.
Construction is scheduled to take place in 2024-2026.
These roadways are in need of long-term improvements to address aging infrastructure, safety, and access issues. This project will resurface deteriorating pavement, replace storm sewer, and incorporate landscaping along the project area.
2024: Resurface Hwy 11 south of the bridge and Cedar Ave. Begin Hwy 11/313 roundabout.
2025: Construct Highway 11/313 roundabout. Begin half of the bridge construction.
2026: Continue other half of the bridge construction.
The bridge will be constructed in 2025 and 2026. The bridge will remain open during the winter months.
How about a roundabout?
Traffic impacts:
 Stage 3: Construct north leg of the roundabout. Hwy 313 will be closed during this stage, approximately 2-3 weeks. See detour map.
  The truck detour is in place for the duration of the project. The Hwy 313 detour will only be in place during Stage 3 of the project.
www.511mn.org
Visit: mndot.gov/d2/projects/hwy11-warroad
|