 Stage 3 of the roundabout construction is underway. Highway 313 motorists will detour using Gladys, Main St. and CR 74. See detour map. Highway 11 east, west and south legs of the roundabout are open to traffic. Motorists are encouraged to use additional caution in the work zone.
Highway 11 Warroad Construction: August 21
What's happening this week?
August 18-22
-
Traffic impacts: Truck detour in place. Highway 313 detour in place. Single lane traffic with temporary lights at Warroad River bridge. See detour maps.
-
Bridge project – Piers were cast and curing period begins. Crews will begin setting beams late in the week.
-
Roundabout project (Stage 3) – Crews have completed grading for Hwy 313 (north leg of roundabout). Finishing up storm sewer installation. Curb and gutter will begin being placed on Hwy 313.
What's happening next week?
August 25-29
-
Traffic impacts: Truck detour in place. Highway 313 detour in place. Single lane traffic with temporary lights at Warroad River bridge. See detour maps.
-
Bridge project – Beam setting will continue and should wrap up the end of the week.
-
Roundabout project (Stage 3) –Concrete will be poured on Hwy 313. Curb and gutter will be placed on north side of Hwy 11.
About the project:
MnDOT, in collaboration with Roseau County and the City of Warroad, plans to reconstruct Highway 11 between County Road 5 and Highway 313/Cedar Avenue NW and Cedar Avenue NW between Highway 11 and Lake Street.
Construction is scheduled to take place in 2024-2026.
These roadways are in need of long-term improvements to address aging infrastructure, safety, and access issues. This project will resurface deteriorating pavement, replace storm sewer, and incorporate landscaping along the project area.
2024: Resurface Hwy 11 south of the bridge and Cedar Ave. Begin Hwy 11/313 roundabout.
2025: Construct Highway 11/313 roundabout. Begin half of the bridge construction.
2026: Continue other half of the bridge construction.
The bridge will be constructed in 2025 and 2026. The bridge will remain open during the winter months.
How about a roundabout?
Traffic impacts:
 Stage 3: Construct north leg of the roundabout. Hwy 313 will be closed during this stage, approximately 2-3 weeks. See detour map.
  The truck detour is in place for the duration of the project. The Hwy 313 detour will only be in place during Stage 3 of the project.