 Highway 200 Itasca State Park project update: July 24
What's happening this week?
July 21-26
-
Traffic impacts: Detour is in place- see map.
- Final shaping at two culverts on the western end of the project
- Final shaping at culvert near the center of the project
- Starting the removal of the centerline culvert at Lasalle Creek
What's happening next week?
July 28-August 1
-
Traffic impacts: Detour is in place- see map.
- Final shaping of culvert at Lasalle Creek
- Grading the shoulder reconstruct area (Farthest east end of the project)
This project began on July 8 and includes resurfacing Highway 200 from Clearwater County Road 2 to Highway 71 near the Itasca State Park. The project also includes culvert and guardrail replacements. The project is expected to be complete late-August, weather permitting.
Highway 200 between Clearwater County Road 2 and Highway 71 will be detoured during construction, but residents and businesses will be able to access their properties. Thru traffic will not be allowed to ensure safety of the workers. Thru traffic will be detoured onto Hubbard County Roads 3 and 9, as well as Clearwater County Roads 2, 40 and 37.
The North and East entrances of the Itasca State Park will remain open throughout construction.
For more information on the project, please visit www.mndot.gov/d2/projects/hwy200-itasca-state-park .
Visit: www.mndot.gov/d2/projects/hwy200-itasca-state-park
|
|
|
MnDOT invites and encourages participation by all people in their programs, services and activities. If you need an ASL, a foreign language interpreter, or documents in an alternative format (such as braille, large print or in a different language) at no cost, please email your request to Janet Miller at ADArequest.dot@state.mn.us or call 651-366-4720. Relay service: 711.