   Detour A is expected to be in place for most of the project. Detour B will take place later this summer and is expected to last approximately two weeks.
 Highway 11 Roseau Project Update: June 20
What's happening this week?
June 16-21
- Crews will continue pouring new sidewalk on south side of Highway 11
- Driveway aprons being poured and turf establishment begins
- Installation of storm sewer at Main Ave heading west
What's happening next week?
June 23-28
- Construction activities will move to north side of Highway 11 starting with sidewalk removals
- Storm sewer will continue to be installed west of the Roseau River Bridge
This project includes resurfacing, sidewalk upgrades, signal removal, bridge improvements, lighting and utility upgrades. Motorists can expect a detour using Center Street West.
Benefits include a safer road, safer intersections, longer lasting driving surface, and improved drainage and pedestrian accessibility. It is expected to be complete early-September, weather permitting. For more information and to sign up for email updates, visit mndot.gov/d2/projects/hwy11-roseau.
For real-time traffic and travel information in Minnesota, visit www.511mn.org or get the free smartphone app at Google Play or the App Store.

|
|
|
MnDOT invites and encourages participation by all people in their programs, services and activities. If you need an ASL, a foreign language interpreter, or documents in an alternative format (such as braille, large print or in a different language) at no cost, please email your request to Janet Miller at ADArequest.dot@state.mn.us or call 651-366-4720. Relay service: 711.