  Stage 2: Construct east, west and south legs of the roundabout. Cedar Avenue will be closed at Hwy 11 during this stage, approximately 3-4 months.
Highway 11 Warroad Construction: June 6
What's happening this week?
June 2-6 (Hwy 11/313 roundabout)
-
Traffic impacts: Cedar Ave closed at the roundabout (Stage 2)
- Pavement milling on eastbound lanes
- Contractor closed down south portion of highway and moved traffic onto bypass
- Sidewalk and curb removal on Hwy 11
What to expect next week?
June 9-13 (Hwy 11 Warroad River bridge project begins)
- Temporary stop light and one lane traffic will begin at Warroad river bridge crossing. Motorists can expect delays.
- Bridge project will begin Monday
- Bridge demo will begin
- Contractor will continue working on or near roundabout
About the project:
MnDOT, in collaboration with Roseau County and the City of Warroad, plans to reconstruct Highway 11 between County Road 5 and Highway 313/Cedar Avenue NW and Cedar Avenue NW between Highway 11 and Lake Street.
Construction is scheduled to take place in 2024-2026.
These roadways are in need of long-term improvements to address aging infrastructure, safety, and access issues. This project will resurface deteriorating pavement, replace storm sewer, and incorporate landscaping along the project area.
2024: Resurface Hwy 11 south of the bridge and Cedar Ave. Begin Hwy 11/313 roundabout.
2025: Construct Highway 11/313 roundabout. Begin half of the bridge construction.
2026: Continue other half of the bridge construction.
The bridge will be constructed in 2025 and 2026. The bridge will remain open during the winter months.
How about a roundabout?
Traffic impacts:
 Once Stage 2 of the roundabout construction is complete, Stage 3 will begin. Stage 3: Construct north leg of the roundabout. Hwy 313 will be closed during this stage, approximately 2-3 weeks. See detour map.
 The truck detour is in place for the duration of the project. The Hwy 313 detour will only be in place during Stage 3 of the project which will take place toward the end of the project and last approximately 2-3 weeks, weather permitting.
www.511mn.org
Visit: mndot.gov/d2/projects/hwy11-warroad
|