Highway 11 Warroad project update: June 14
What's happening now?
- Crews finished installing storm sewer on the west side of Hwy 11
- They began sub cutting the road core and replacing with new aggregate
- Many city water line connections on side streets were replaced along with sanitary sewer replacements
- On Cedar Ave., crews began delivering storm sewer materials to the site for staging
- Storm sewer outlet structures were installed near Lake St.
What's next?
- Storm sewer installation will progress north on Cedar Ave.
- City utility work on side streets will continue south of the Warroad river bridge on Hwy 11
- Subcut work on Hwy 11 will continue and crews will prepare grade for curb/gutter and sidewalk
Traffic Impact:
The contractor for this $17.5 million dollar project is Spruce Valley. This project will create a safer, longer lasting driving surface as well as improve drainage, pedestrian accessibility, and a safer intersection. It is estimated to be complete by October 2024, and resume in the spring of 2025, weather permitting. Visit the project website below for more information, sign up for email updates, as well as a project map: www.mndot.gov/d2/projects/hwy11-warroad.
Important reminders for motorists regarding work zone safety:
- Slow down when approaching every work zone, then navigate through with care and caution.
- Stay alert; work zones constantly change.
- Watch for workers and slow-moving equipment.
- Obey posted speed limits. Fine for a violation in a work zone is $300.
- Minimize distractions behind the wheel.
- Be patient; expect delays, especially during peak travel times.
Please join the MnDOT District 2 Facebook group for updates on construction, road conditions and other transportation related topics. www.facebook.com/groups/mndotnorthwest/. For a complete list of projects for 2021, please visit www.mndot.gov/d2. For real-time traffic and travel information in Minnesota, visit www.511mn.org or get the free smartphone app at Google Play or the App Store.
Visit: http://www.mndot.gov/d2/projects/hwy11-warroad
|
|
MnDOT invites and encourages participation by all people in their programs, services and activities. If you need an ASL, a foreign language interpreter, or documents in an alternative format (such as braille, large print or in a different language) at no cost, please email your request to Janet Miller at ADArequest.dot@state.mn.us or call 651-366-4720. Relay service: 711.