Highway 34 Akeley: May 31 update
 What's happening now?
- This week crews continued grading and began paving
- Landscaping, hydroseeding
- Install light poles
- Detour lifted
What's next?
Next week, crews will continue punchlist of items to complete. In the next few weeks, crews will repair drains at Zappy's. Once complete, the final lift of pavement will be placed followed by striping.
Stage 3
- Reclaim Hillside Ave. to Fire Hall
- Storm sewer
- Concrete removals
Traffic impact: Detour lifted, use caution in work zone
The project is expected to be complete in mid-June, weather permitting. For more information as well as staging and detour maps, visit the project website: www.mndot.gov/d2/projects/hwy34-akeley
Stay connected
For more information on projects in northwest Minnesota, follow us on Facebook at https://facebook.com/groups/MnDOTnorthwest and Twitter at @mndotnorthwest. For real-time traffic and travel information in Minnesota, visit www.511mn.org.
https://www.dot.state.mn.us/d2/projects/hwy34-akeley/index.html
|