Highway 34 Akeley: May 23 update
What's happening now?
This week crews continued grading and began concrete work. Concrete work will continue next week.
What's next?
Next week, crews will begin paving mid-week and begin to install light poles. Once paving is complete, the detour will be lifted. There will be punch list items to complete after paving, but the project still remains on schedule with estimated completion mid-June.
*Reminder to motorists- Although striping will be complete after paving operations, please continue to obey traffic laws and avoid passing on the shoulder. Drive safe!
Stage 3
- Reclaim Hillside Ave. to Fire Hall
- Storm sewer
- Concrete removals
Traffic impact: Detour utilizing Hubbard CR 25 and Highway 64
The project is expected to be complete in mid-June, weather permitting. For more information as well as staging and detour maps, visit the project website: www.mndot.gov/d2/projects/hwy34-akeley
Stay connected
For more information on projects in northwest Minnesota, follow us on Facebook at https://facebook.com/groups/MnDOTnorthwest and Twitter at @mndotnorthwest. For real-time traffic and travel information in Minnesota, visit www.511mn.org.
https://www.dot.state.mn.us/d2/projects/hwy34-akeley/index.html
|
|
Tell us what you think!
We are looking for feedback for our Gov Delivery services and would like to hear from you. Your comments are valuable to us. Tap the button below to participate.
|
|
MnDOT invites and encourages participation by all people in their programs, services and activities.
If you need an ASL, a foreign language interpreter, or documents in an alternative format (such as braille, large print or in a different language) at no cost, please email your request to Janet Miller at ADArequest.dot@state.mn.us or call 651-366-4720. Relay service: 711.
If you need any other reasonable accommodation to participate (such as seating modification or auxiliary aids), please email your request to Accessibility.DOT@state.mn.us or call 1-833-400-8432. Relay service: 711.
|
|
|
|