Traffic will be detoured through October 2023
The detour for the Hwy 14 New Ulm to Nicollet four-lane expansion project is expected to begin Monday, April 11, weather permitting, as crews begin construction on the 12.5-mile corridor. The detour will remain in place until the completion of the project in October 2023.
Through traffic will be detoured onto Highways 15, 68 and 169 for the duration of the project. Detour routes and access points for local traffic are expected to change throughout different stages of construction. Detour maps can be found online at: https://www.dot.state.mn.us/d7/projects/14newulmtonmankato/index.html.
MnDOT will be reconstructing Hwy 14 from New Ulm to Nicollet between 2022-2023 to improve safety and travel for this important freight and trade corridor. Overall, the project is expanding 12.5 miles of Hwy 14 from two lanes to four lanes between New Ulm and Nicollet to complete a continuous four-lane road between New Ulm and Rochester.
Improvements will include:
- Converting the existing two-lane highway to a four-lane divided highway
- Bypassing Courtland by realigning Hwy 14 north of the city
- Constructing new interchanges in Courtland and at Co. Rd. 37 in New Ulm
- Constructing safer intersections at New Ulm Quartzite Quarries and Minnesota Valley Lutheran High School
- Adding turn lanes
- Installing snow fence between Courtland and Nicollet to prevent excessive blowing and drifting snow
Hoffman Construction was awarded the project with a bid of $83,539,141.56.
Stay connected, informed
|
|
MnDOT invites and encourages participation by all. If you need an ASL, a foreign language interpreter, or other reasonable accommodation, or need documents in an alternative format (such as braille or large print), please email your request to Janet Miller at ADArequest.dot@state.mn.us or call 651-366-4720. |
|
|
|