Currently, crews are focused on the Stage 5 culvert work. Local traffic will encounter short-term closures and periodic stops in the areas where crews are working. Watch for loose gravel, heavy equipment and workers. Access is being maintained to driveways, but the direction of travel to exit/enter the work zone may change daily. If you live on the roadway, please feel free to check in with the crews on-site if you have questions about where to go.
Additionally, crews have also started the Stage 5 shoulder widening and ditch grading.
As for the rest of the project, paving has started in Stages 3 and 4. This operation will move west to east, starting in Stage 4 at County Road 21, heading east to County Road 80 in Stage 3.
|