2021 Construction: Hwy 87 Frazee to Becker/Wadena County Line
Reclaiming and paving continue on Highway 87 between Frazee and Evergreen! At this time, reclaiming is nearly complete, and crews are expected to finish paving by next weekend. There is still a lot that will have to be done before the roadway can reopen, so we appreciate your patience as we move into the final stretch of construction.
As crews pave, they're likely to be in various locations daily. Local traffic: remain alert for changing work zones and travel with caution. You will continue to encounter pilot cars and lane closures between Frazee and Evergreen. Please wait and follow the pilot car. Expect short delays.
In addition to reclaiming and paving, crews are also putting finishing touches on the new bridge at the Otter Tail River. Until guardrail is in place, Highway 87 remains impassable at the bridge site, between North River Drive and Main Avenue East. Please continue to use an alternate route.
All Highway 87 thru-traffic: follow the detour route on Highway 71, Highway 34 and County Road 29/Birch Avenue.
- Culvert work between Frazee and Evergreen
- Majority of the bridge replacement at the Otter Tail River
- Finish shoulder widening near Evergreen
- Install guardrail, finish turf establishment at the Otter Tail River bridge
- Finish reclaiming
- Paving
For more detailed project information visit the project website.
|
|
MnDOT invites and encourages participation by all. If you need an ASL, a foreign language interpreter, or other reasonable accommodation, or need documents in an alternative format (such as braille or large print), please email your request to Janet Miller at ADArequest.dot@state.mn.us or call 651-366-4720. |
|
|
|