Construction will take place over two years, starting July 19, 2021. The work taking place this year will focus on Highway 55, which will be detoured through October. Crews will realign Highway 55, moving it closer to the railroad to minimize the length of the future bridge on Highway 29. In addition, they will reconstruct 160th Street and build the roundabout at the Highway 55/160th Street intersection.
In Spring 2022, crews will return to begin construction of the Highway 29 bridge and second roundabout at the Highway 29/160th Street intersection.
|
|
|