TRF Project Update: July 10, 2020
Here's what's happening now
Progress, progress progress! YAY the Hwy 32 detour is planned to be lifted on Tuesday, July 14. Crews will be striping on Monday, weather permitting. Each project is listed below with the project update and upcoming schedule.
Thank you TRF for working with us through this busy construction season. We continue to be available for project specific questions or comments at our weekly virtual public meeting. Representatives from Red Lake Watershed, Pennington County and MnDOT will be available during the meeting. Join us on Tuesday, July 14 at 10:00 a.m. Register via the website or see details below.
Project Updates
MnDOT
Hwy 1 Roundabouts in TRF
- This week: Crews continuted installing drainage structures and grading. They began pouring concrete curb on the roundabout at Brooks Ave.
- Next week: The same work details will continue next week.
- Traffic Impacts: Detour onto 1st St W
- Website: www.mndot.gov/d2/projects/2020/hwy1-roundabouts
Hwy 32 Resurface between TRF and St. Hilaire
- This week: Paving from St. Hilaire to TRF is now complete. Rumble strips have been installed.
- Next week: Striping will take place on Monday, weather permitting, which would allow for the detour to be lifted on Tuesday.
- Traffic Impacts: Within the city of St. Hilaire, the work will be completed under traffic with flaggers and lane closures. Detour will continue on Highway 32 and will be lifted on Tuesday:
- Motorists will use CR 3, CR 20 and Highway 59.
- Traffic coming from south headed north, must take detour.
- From the north, going to hospital can still get through, using flaggers on site. Only able to get to hospital, not further south.
- Residents will have access maintained.
- Detour lifted on Tuesday, July 14, weather permitting.
- Website: www.mndot.gov/d2/projects/2020/hwy32-resurface
Hwy 1 Resurfacing east of TRF
Pennington County
Hwy 32 Roundabout at CR 8/Mark Blvd
- This week: Curb and gutter on Phase 1 will be complete this week.
- Next week: Prepare to begin paving the week of July 20. Phase 2 will include the construction f the Mark Boulevard leg of the roundabout.
- Traffic Impacts: Continued use of bypass lane
- Website: www.mndot.gov/d2/projects/2020/hwy32-roundabout
CR 8/Mark Blvd route extension and roundabout
- This week: Crews have been working on installing beams in the middle span of the bridge. Water levels have delayed the work. Crews have been progressing on the Challenger School roundabout with grading and installation of aggregate.
- Next week: Aggregate installation will continue between the roundabout and the bridge.
- Traffic Impacts: The intersection at Pennington Ave near Challenger Elementary is currently closed and a detour is in place.
- Detour onto Greenwood St, Hwy 59 and 140th St NE (See picture below)
- Website: www.mndot.gov/d2/projects/2020/airport-road-roundabout
Red Lake Watershed
Westside flood damage reduction Projects
www.mndot.gov/d2/projects/2020/westside-drainage-project
- Construct a diversion channel and drainage infrastructure on the west side of TRF. Underground storm sewer will be installed along Barzen Ave and Greenwood St, along with a new sanitary sewer
- This week: Crews began boring the 54" steel casing pipe.
- Next week: Excavation of the outlet, east of Hwy 32 will begin early next week.
- Traffic Impacts: Shoulder closure along Greenwood St., Oakland park Rd., and Highway 32. Shoulder closure on the north side of Greenwood St. from TH 32 to Oakland Park Rd
- Website: www.mndot.gov/d2/projects/2020/westside-drainage-project
- Replace Hwy 1 culvert west of the intersection with Hwy 59
- This week:
- Next week:
- Traffic Impacts: Once this project begins, motorists will detour onto 190th St NE and CR 14
- Replace Hwy 32 culvert south of Pennington CR 7
- This week: Culvert installation is complete.
- Next week: The subcontractor will begin forming the inlet end section in the next few weeks.
- Traffic Impacts: Detour will continue. Motorists use CR 3, CR 20 and Highway 59.
- Traffic coming from south headed north, must take detour.
- From the north, motorists going to the hospital can still get through, using flaggers on site. However they will not be able to travel further south.
- Residents will have access maintained
- Once crews begin formting the inlet at the culvert site, there will be a shoulder closure on the west side. However, the detour will be lifted on Tuesday, July 14, weather permitting.
Next meeting is on July 14th at 10 a.m., register now:
-
Register prior to the meeting and a confirmation email message will be sent with instructions on how to join the meeting. You can also register just prior to joining the meeting.
-
The meeting link and phone number access code will change every week. The project website has up-to-date information and it will be emailed each week as well.
- If attendees haven’t joined a Webex online meeting before, it’s suggested to join the meeting at least 15 minutes early to allow enough time for any set up requirements. The Webex Help Center provides instructions and troubleshooting information.
- Register for future meetings:
To join by computer
To join via phone for audio only
- Dial 1-855-282-6330 or 415-655-0003
- When prompted, use Access Code: 146 060 3533
Project questions? Prior to the meeting, attendees can submit questions through the Comment form on the project website. In the online meeting, attendees are able to submit questions through a Chat feature.
To request reasonable accommodations, call 651-366-4720 or email your request to adarequest.dot@state.mn.us.
Visit: www.mndot.gov/d2/projects/2020/thief-river-falls
|